260 S UNION AVE 90026
Certificate Information: 260 S UNION AVE 90026
- Application / Permit
- 22016-10000-01434
- Plan Check / Job No.
- B22LA00759
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (1) SPECIAL CANTILEVERED COLUMN WITH GRADE BEAM
- Permit Issued
- Issued on 4/19/2022
- Issuing Office
- Current Status
- CofC Issued on 4/30/2025
Permit Application Status History
| Submitted | 2/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | HANS SANTIAGO |
| Corrections Issued | 2/28/2022 | HANS SANTIAGO |
| Quality Review Completed | 3/1/2022 | SAI KHUM |
| Applicant returned to address corrections | 4/4/2022 | HANS SANTIAGO |
| Plan Check Approved | 4/14/2022 | ANDREW SANTIAGO |
| Issued | 4/19/2022 | APPLICANT |
| OK for CofC | 4/30/2025 | DARRYL ARNOLD |
| CofC Issued | 4/30/2025 | WINSTON DUNNING |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 3/7/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 3/30/2022 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 4/19/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/28/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 5/5/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/10/2022 | Corrections Issued | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 5/17/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 5/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/20/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 5/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 5/26/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| METHANE-Final | 5/26/2022 | Approved | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Not Ready | BRUCE CAMPBELL |
| Smoke Detectors | 5/26/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| Final | 4/10/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/10/2025 | Conditional Approval | DARRYL ARNOLD |
| Final | 4/30/2025 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 4/30/2025 | Approved | DARRYL ARNOLD |