444 S FLOWER ST 90071
Certificate Information: 444 S FLOWER ST 90071
- Application / Permit
- 22016-10000-01261
- Plan Check / Job No.
- B22LA00693
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- eplan TENANT IMPROVEMENT TO EXISTING OFFICE SPACE; CONVERT PORTION OF OFFICE SPACE TO WALKING DECK
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- Permit Finaled on 9/12/2022
Permit Application Status History
| Submitted | 1/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | SELLA BENYAMIN |
| Corrections Issued | 1/20/2022 | SELLA BENYAMIN |
| Plan Check Approved | 2/3/2022 | SELLA BENYAMIN |
| Issued | 3/24/2022 | APPLICANT |
| Permit Finaled | 9/9/2022 | TIMOTHY BUXTON |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/31/2022 | YI LU |
Contact Information
| Contractor | Kprs Construction Services Inc; Lic. No.: 751130-B | 2850 SATURN STREET BREA, CA 92821 |
| Engineer | Cocke,, David Winbern; Lic. No.: S3005 | 19210 S VERMONT AVENUE BLDNG B SUITE 210 GARDENA, CA 90248 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 5/23/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Steel/Welding | 6/9/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 6/10/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 6/13/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 6/14/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Drilled-In Anchors | 6/16/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 6/16/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 6/28/2022 | Conditional Approval | ERNESTO CORRAL |
| Structural Steel Frame | 6/28/2022 | Approved | TIMOTHY BUXTON |
| Structural Steel Frame | 6/29/2022 | Partial Approval | TIMOTHY BUXTON |
| Deputy Fireproofing | 7/15/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Insulation | 7/18/2022 | Partial Approval | BRUCE CAMPBELL |
| Drywall Nailing | 7/21/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 8/5/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 8/8/2022 | Approved | TIMOTHY BUXTON |
| Final | 9/9/2022 | Permit Finaled | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 9/9/2022 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 9/9/2022 | Approved | TIMOTHY BUXTON |