4617-4619 E PAULA ST 90032

Certificate Information: 4617-4619 E PAULA ST 90032

Application / Permit
22016-10000-01209
Plan Check / Job No.
B22LA00663
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Remodel of both units. Remodel of kitchen and bathrooms. Relocate main entry door for one unit and remove kitchen exterior door.
Permit Issued
Issued on 1/21/2022
Issuing Office
Current Status
Permit Finaled on 9/8/2022

Permit Application Status History

Submitted 1/14/2022 APPLICANT
Assigned to Plan Check Engineer 1/18/2022 RICARDO RAMIREZ
Plan Check Approved 1/18/2022 RICARDO RAMIREZ
Issued 1/21/2022 APPLICANT
Building Plans Picked Up 1/24/2022 APPLICANT
Permit Finaled 9/7/2022 AMY COLIN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/27/2022 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 2/3/2022 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 2/3/2022 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 2/3/2022 Partial Inspection COREY HUPP
ELECTRICAL-Rough 2/24/2022 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 2/24/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/24/2022 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 2/25/2022 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/2/2022 Approved COREY HUPP
HVAC-Rough 3/2/2022 Approved COREY HUPP
Interior/Exterior Lathing 3/2/2022 Approved COREY HUPP
PLUMBING-Rough 3/2/2022 Not Ready for Inspection COREY HUPP
Rough-Elec/Plmb/HVAC 3/7/2022 Approved COREY HUPP
Insulation 3/8/2022 Approved SCOTT FINNILA
Drywall Nailing 3/16/2022 Approved AMY COLIN
Interior/Exterior Lathing 3/30/2022 Partial Approval AMY COLIN
Interior/Exterior Lathing 4/1/2022 Approved AMY COLIN
HVAC-Final 5/25/2022 Corrections Issued AMY COLIN
ELECTRICAL-Final 5/27/2022 Corrections Issued SHAVONNE ESPINOZA
Final 5/27/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Gas Test 5/27/2022 Approved SHAVONNE ESPINOZA
PLUMBING-Final 5/27/2022 Approved SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 5/27/2022 SGSOV Approved SHAVONNE ESPINOZA
Smoke Detectors 5/27/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Final 6/2/2022 Approved AMY COLIN
Final 6/2/2022 Partial Inspection AMY COLIN
HVAC-Final 6/2/2022 Approved AMY COLIN
PLUMBING-Final 6/2/2022 Corrections Issued AMY COLIN
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Approved AMY COLIN
Smoke Detectors 6/2/2022 Approved AMY COLIN
Final 9/7/2022 Permit Finaled AMY COLIN
PLUMBING-Final 9/7/2022 Approved AMY COLIN
Smoke Detectors 9/7/2022 Approved AMY COLIN