1700 S MALCOLM AVE 90024

Certificate Information: 1700 S MALCOLM AVE 90024

Application / Permit
22016-10000-01153
Plan Check / Job No.
B22LA00639
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install 2 Special Steel Cnatilever Columns
Permit Issued
Issued on 7/7/2022
Issuing Office
Current Status
CofC Issued on 6/1/2023

Permit Application Status History

Submitted 1/13/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 VARAND SARKISIAN
Corrections Issued 2/17/2022 VARAND SARKISIAN
Quality Review Completed 2/23/2022 SAI KHUM
Applicant returned to address corrections 3/21/2022 VARAND SARKISIAN
Plan Check Approved 5/2/2022 VARAND SARKISIAN
Issued 7/7/2022 APPLICANT
OK for CofC 5/2/2023 MICHAEL PETRUSKO
CofC Issued 6/1/2023 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Specific Plan Cleared 3/29/2022 KEVIN FULTON
Tenant Habitability Plan Cleared 7/6/2022 RICARDO BOHORQUEZ

Contact Information

Contractor Optimum Seismic Inc; Lic. No.: 1012702-B 5508 S SANTA FE AVENUE      VERNON, CA 90058
Engineer Kenan, Park; Lic. No.: C86314       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/15/2022 No Access for Inspection GRANT WOODS
Pre-Inspection 7/22/2022 Approved SORIN CIRSTOIU
Structural Steel Frame 7/29/2022 Not Ready for Inspection GRANT WOODS
Wood Frame 7/29/2022 Not Ready for Inspection GRANT WOODS
Deputy Wood Construction 8/1/2022 Conditional Approval PAUL DAVIDSON
Wood Frame 8/1/2022 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 8/2/2022 Partial Approval GRANT WOODS
Deputy Drilled-In Anchors 8/18/2022 Conditional Approval GRANT WOODS
Deputy Steel/Welding 8/24/2022 Conditional Approval GRANT WOODS
Deputy Wood Construction 8/25/2022 Approved GRANT WOODS
Footing/Foundation/Slab 8/25/2022 Approved GRANT WOODS
Structural Steel Frame 8/25/2022 Approved GRANT WOODS
Wood Frame 8/25/2022 Approved GRANT WOODS
Interior/Exterior Lathing 9/12/2022 Approved PAUL DAVIDSON
Final 5/2/2023 Partial Inspection MICHAEL PETRUSKO
METHANE-Final 5/2/2023 Approved MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 5/2/2023 SGSOV Approved MICHAEL PETRUSKO
Smoke Detectors 5/2/2023 Approved MICHAEL PETRUSKO