825 W 165TH PL 1-9 90247

Certificate Information: 825 W 165TH PL 1-9 90247

Application / Permit
22016-10000-00884
Plan Check / Job No.
B22LA00503
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePlan: (N) ACCESSORY DWELLING UNIT ADDITION TO (E) 2-STORY APARTMENT PER LAMC 12.22.A.33(c) AND (e).
Permit Issued
Issued on 9/9/2023
Issuing Office
Current Status
Issued on 9/9/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/13/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 DANIEL YIP
Corrections Issued 2/15/2022 DANIEL YIP
Quality Review Completed 2/15/2022 LIPING TENG
Plan Check Approved 4/8/2022 DANIEL YIP
Issued 9/9/2023 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 2/28/2022 MICHAEL SOTO
Address approval Cleared 3/2/2022 JOSE HERNANDEZ
Roof/Waste drainage to street Cleared 3/2/2022 JOSE HERNANDEZ
Sewer availability Cleared 3/3/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 3/8/2022 JOSE HERNANDEZ
DAS Clearance Cleared 3/16/2022 DANIEL YIP
Green Code Cleared 3/24/2022 DANIEL YIP

Contact Information

Contractor Snow Construction La Llc; Lic. No.: 1016716-B       ,
Contractor Snow Construction; Lic. No.: 1016716-B       ,

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/13/2023 Partial Approval AMANUEL BERHE
Deputy Drilled-In Anchors 11/3/2023 Conditional Approval AMANUEL BERHE
Footing/Foundation/Slab 11/17/2023 Approved AMANUEL BERHE
Drywall Nailing 12/13/2023 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Not Ready for Inspection JOEY BUCHANAN
Green Building Rough 12/13/2023 Approved JOEY BUCHANAN
Wood Frame 12/13/2023 Corrections Issued JOEY BUCHANAN
Deputy Wood Construction 1/3/2024 Approved JOEY BUCHANAN
Wood Frame 2/6/2024 Corrections Issued AMANUEL BERHE
Wood Frame 2/14/2024 Not Ready for Inspection AMANUEL BERHE
Wood Frame 2/20/2024 Partial Inspection AMANUEL BERHE
Insulation 2/23/2024 Approved AMANUEL BERHE
Drywall Nailing 3/4/2024 Corrections Issued JOEY BUCHANAN
Pre-Inspection 5/7/2024 Approved AMANUEL BERHE
Deputy Drilled-In Anchors 5/13/2024 Conditional Approval AMANUEL BERHE
Pre-Inspection 5/13/2024 Approved AMANUEL BERHE
Drywall Nailing 5/22/2024 Approved AMANUEL BERHE
Final 5/22/2024 Partial Inspection AMANUEL BERHE
Green Building Final 5/22/2024 Approved AMANUEL BERHE
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Approved AMANUEL BERHE
Smoke Detectors 5/22/2024 Not Ready for Inspection AMANUEL BERHE
Wood Frame 5/22/2024 Approved AMANUEL BERHE
Final 1/24/2025 Not Ready for Inspection MICHAEL PETRUSKO
Smoke Detectors 1/24/2025 Not Ready for Inspection MICHAEL PETRUSKO