105 S HAYWORTH AVE 90048
Certificate Information: 105 S HAYWORTH AVE 90048
- Application / Permit
- 22016-10000-00832
- Plan Check / Job No.
- B22LA00466
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install (N) SCCS.
- Permit Issued
- Issued on 4/27/2022
- Issuing Office
- Current Status
- CofC Issued on 10/12/2022
Permit Application Status History
| Submitted | 1/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | VARAND SARKISIAN |
| Corrections Issued | 2/1/2022 | VARAND SARKISIAN |
| Quality Review Completed | 2/8/2022 | SAI KHUM |
| Plan Check Approved | 3/3/2022 | VARAND SARKISIAN |
| Issued | 4/27/2022 | APPLICANT |
| OK for CofC | 10/5/2022 | BRUCE CAMPBELL |
| CofC Issued | 10/12/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/14/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/13/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| Pre-Inspection | 6/10/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 6/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 7/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Other (see comments) | 7/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 7/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 7/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 7/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 7/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 7/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 8/8/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 10/5/2022 | OK for CofC | BRUCE CAMPBELL |
| METHANE-Final | 10/5/2022 | Approved | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 10/5/2022 | Approved | BRUCE CAMPBELL |