534 W 104TH PL 90044
Certificate Information: 534 W 104TH PL 90044
- Application / Permit
- 22016-10000-00740
- Plan Check / Job No.
- B22LA00428
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ADU WITH NEW COVERED PORCH PER DETACHED ADU PER ORDINANCE (1-STORY) COMPLY WITH DEPARTMENT ORDER effective date 11/19/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 10/11/2022
- Issuing Office
- Current Status
- CofO Issued on 1/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | PRANITA SHAH |
| Corrections Issued | 1/28/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 8/12/2022 | PRANITA SHAH |
| Plan Check Approved | 9/28/2022 | PRANITA SHAH |
| Issued | 10/11/2022 | APPLICANT |
| CofO in Progress | 12/11/2024 | MICHAEL SERETTI |
| CofO in Progress | 12/17/2024 | JAVIER RAMOS SR |
| CofO in Progress | 1/24/2025 | MICHAEL SERETTI |
| Permit Finaled | 1/24/2025 | CLAUDIO MORENO |
| CofO Issued | 1/24/2025 | CLAUDIO MORENO |
| Permit Finaled | 1/24/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 3/17/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 3/17/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2022 | TREVOR QUAN |
| Construction near power lines | Cleared | 7/14/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/22/2022 | Approved | KIM DOEPPING |
| Pre-Inspection | 3/8/2023 | Partial Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 4/27/2023 | Corrections Issued | ENRIQUE PREZA |
| Footing/Foundation/Slab | 5/3/2023 | Partial Approval | DANIEL GONZALEZ |
| Underground Mechanical | 5/3/2023 | Not Ready for Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 6/12/2023 | Partial Approval | EUSEBIO GUZMAN |
| PLUMBING-Rough | 6/12/2023 | Not Ready for Inspection | EUSEBIO GUZMAN |
| PLUMBING-Rough | 6/13/2023 | Not Ready for Inspection | EUSEBIO GUZMAN |
| Footing/Foundation/Slab | 6/30/2023 | Approved | EUSEBIO GUZMAN |
| PLUMBING-Rough | 6/30/2023 | Not Ready for Inspection | EUSEBIO GUZMAN |
| PLUMBING-Rough | 8/10/2023 | Not Ready for Inspection | EUSEBIO GUZMAN |
| Pre-Inspection | 8/10/2023 | Approved | EUSEBIO GUZMAN |
| PLUMBING-Rough | 9/11/2023 | Corrections Issued | EUSEBIO GUZMAN |
| PLUMBING-Rough | 9/13/2023 | Not Ready for Inspection | EUSEBIO GUZMAN |
| Wood Frame | 9/13/2023 | Not Ready for Inspection | EUSEBIO GUZMAN |
| Wood Frame | 9/19/2023 | Not Ready for Inspection | EUSEBIO GUZMAN |
| BUILDING-Rough-Frame | 10/27/2023 | Partial Approval | EUSEBIO GUZMAN |
| Green Building Rough | 10/27/2023 | Not Ready for Inspection | EUSEBIO GUZMAN |
| Wood Frame | 10/27/2023 | Not Ready for Inspection | EUSEBIO GUZMAN |
| ELECTRICAL-Rough | 1/4/2024 | Approved | JOHN PARKER |
| Insulation | 1/30/2024 | Approved | JOHN PARKER |
| Interior/Exterior Lathing | 1/30/2024 | Approved | JOHN PARKER |
| Drywall Nailing | 2/14/2024 | Corrections Issued | MICHAEL SERETTI |
| BUILDING-Rough-Frame | 3/27/2024 | Approved | MICHAEL SERETTI |
| Drywall Nailing | 3/27/2024 | Approved | MICHAEL SERETTI |
| Green Building Rough | 3/27/2024 | Not Ready for Inspection | MICHAEL SERETTI |
| Pre-Inspection | 8/9/2024 | Approved | MICHAEL SERETTI |
| Rough-Elec/Plmb/HVAC | 8/9/2024 | Not Ready for Inspection | MICHAEL SERETTI |
| Rough-Elec/Plmb/HVAC | 8/21/2024 | Approved | MICHAEL SERETTI |
| BUILDING-Rough-Frame | 9/26/2024 | Approved | MICHAEL SERETTI |
| Drywall Nailing | 9/26/2024 | Approved | MICHAEL SERETTI |
| Green Building Final | 9/26/2024 | Approved | MICHAEL SERETTI |
| Green Building Rough | 9/26/2024 | Approved | MICHAEL SERETTI |
| SGSOV-Seismic Gas S/O Valve | 9/26/2024 | SGSOV Approved | MICHAEL SERETTI |
| Smoke Detectors | 9/26/2024 | Approved | MICHAEL SERETTI |
| Final | 11/26/2024 | Corrections Issued | MICHAEL SERETTI |
| Final | 12/17/2024 | Corrections Issued | MICHAEL SERETTI |
| Final | 1/24/2025 | OK to Issue CofO | MICHAEL SERETTI |