Footing/Foundation/Slab
|
3/3/2023
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Pre-Inspection
|
3/3/2023
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Deputy Drilled-In Anchors
|
3/13/2023
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Other (see comments)
|
3/13/2023
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Drilled-In Anchors
|
3/16/2023
|
Conditional Approval
|
ANDREW DORSO
|
|
Footing/Foundation/Slab
|
3/16/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Footing/Foundation/Slab
|
4/5/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Footing/Foundation/Slab
|
4/26/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Footing/Foundation/Slab
|
4/27/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Light Gage Steel Frame
|
5/17/2023
|
Corrections Issued
|
ANDREW DORSO
|
|
Insulation
|
6/22/2023
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Footing/Foundation/Slab
|
6/27/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Insulation
|
6/29/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
6/29/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
7/6/2023
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
7/11/2023
|
Partial Approval
|
CAMERON CHABAN
|
|
Drywall Nailing
|
7/26/2023
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Deputy Drilled-In Anchors
|
8/17/2023
|
Conditional Approval
|
ANDREW DORSO
|
|
Drywall Nailing
|
8/24/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
8/28/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
8/30/2023
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Wood Frame
|
9/1/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
9/8/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/8/2023
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Insulation
|
9/8/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
9/8/2023
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
9/12/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
9/12/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
9/19/2023
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/19/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Insulation
|
9/19/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
9/19/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Light Gage Steel Frame
|
9/19/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
9/22/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
9/28/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Insulation
|
9/28/2023
|
Approved
|
ANDREW DORSO
|
|
Drywall Nailing
|
10/5/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
10/5/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
10/17/2023
|
Partial Approval
|
KENNETH ROBERTS
|
|
Green Building Rough
|
10/17/2023
|
Approved
|
KENNETH ROBERTS
|
|
Wood Frame
|
10/17/2023
|
Partial Approval
|
KENNETH ROBERTS
|
|
Interior/Exterior Lathing
|
10/27/2023
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
11/2/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Wood Frame
|
11/15/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Wood Frame
|
11/21/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
12/5/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
Wood Frame
|
12/7/2023
|
Partial Approval
|
KENNETH ROBERTS
|
|
Drywall Nailing
|
12/13/2023
|
Partial Inspection
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
2/1/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
3/18/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
4/2/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
4/3/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
4/3/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
4/5/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
4/9/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
4/9/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
4/11/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
4/11/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
4/12/2024
|
Partial Approval
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
4/12/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
4/15/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
4/15/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
4/16/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
4/16/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
4/17/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
4/17/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Interior/Exterior Lathing
|
4/22/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
T-Bar Ceiling
|
4/22/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Final
|
5/17/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Green Building Final
|
5/17/2024
|
Approved
|
ANDREW DORSO
|
|
SGSOV-Seismic Gas S/O Valve
|
5/17/2024
|
SGSOV Approved
|
ANDREW DORSO
|
|
Smoke Detectors
|
5/17/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Wood Frame
|
5/17/2024
|
Approved
|
ANDREW DORSO
|
|
Final
|
7/8/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Smoke Detectors
|
7/8/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Final
|
7/26/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Smoke Detectors
|
7/26/2024
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Deputy Drilled-In Anchors
|
8/5/2024
|
Conditional Approval
|
ANDREW DORSO
|
|
Excavation/Setback/Form/Re-Bar
|
8/6/2024
|
Approved
|
ANDREW DORSO
|
|
Final
|
9/9/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
9/9/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
9/12/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
9/12/2024
|
Approved
|
DANNY RODRIGUEZ
|
|
Final
|
11/8/2024
|
OK to Issue CofO
|
ANDREW DORSO
|