8132 1/2 W 4TH ST 90048

Certificate Information: 8132 1/2 W 4TH ST 90048

Application / Permit
22016-10000-00670
Plan Check / Job No.
B22LA00395
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) TWO CAR GARAGE AND REC ROOM (524) CONVERSION INTO ADU
Permit Issued
Issued on 4/6/2022
Issuing Office
Current Status
CofO Issued on 10/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2022 APPLICANT
Assigned to Plan Check Engineer 1/14/2022 JOSEPH RAFOLS
Corrections Issued 1/14/2022 JOSEPH RAFOLS
Applicant returned to address corrections 2/5/2022 FERNANDO FLORES
Plan Check Approved 3/22/2022 FERNANDO FLORES
Issued 4/6/2022 APPLICANT
Building Plans Picked Up 4/14/2022 APPLICANT
CofO in Progress 10/11/2022 EVAN COOPER
Permit Finaled 10/19/2022 DANIEL ORRANTE
CofO Issued 10/19/2022 DANIEL ORRANTE
Permit Finaled 10/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/21/2022 STEVE MELGAR
Abandoned oil well Cleared 1/24/2022 MENOA AGHAJANI
Tenant Habitability Plan Cleared 1/24/2022 JORGE ALCANTAR
Eng Process Fee Ord 176,300 Cleared 1/31/2022 STEVE MELGAR
Sewer availability Cleared 1/31/2022 STEVE MELGAR
Construction near power lines Cleared 3/15/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/20/2022 Corrections Issued EVAN COOPER
Pre-Inspection 4/20/2022 Approved EVAN COOPER
Pre-Inspection 4/27/2022 Approved EVAN COOPER
PLUMBING-Rough 4/29/2022 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 5/3/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 5/3/2022 Partial Approval EVAN COOPER
Sewer 5/3/2022 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 5/4/2022 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 5/5/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 5/16/2022 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 5/16/2022 Not Ready for Inspection EVAN COOPER
Green Building Rough 5/16/2022 Not Ready for Inspection EVAN COOPER
METHANE-Rough 5/16/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 5/16/2022 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 5/20/2022 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 5/20/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 5/20/2022 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 5/31/2022 Not Ready for Inspection EVAN COOPER
HVAC-Rough 5/31/2022 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 6/2/2022 Corrections Issued MICHAEL PELHAM
HVAC-Rough 6/2/2022 Corrections Issued MICHAEL PELHAM
METHANE-Rough 6/2/2022 Approved MICHAEL PELHAM
PLUMBING-Rough 6/2/2022 Corrections Issued MICHAEL PELHAM
BUILDING-Rough-Frame 6/3/2022 Corrections Issued MICHAEL PELHAM
BUILDING-Rough-Frame 6/9/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 6/9/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 6/9/2022 Conditional Approval STEPHANIE SWANSON
PLUMBING-Rough 6/9/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 6/13/2022 Approved EVAN COOPER
ELECTRICAL-Rough 6/13/2022 Approved EVAN COOPER
Green Building Rough 6/13/2022 Approved EVAN COOPER
HVAC-Rough 6/13/2022 Approved EVAN COOPER
Insulation 6/13/2022 Approved EVAN COOPER
PLUMBING-Rough 6/13/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 6/15/2022 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Approved EVAN COOPER
Drywall Nailing 6/28/2022 Approved EVAN COOPER
Interior/Exterior Lathing 6/28/2022 Not Ready for Inspection EVAN COOPER
Shower Pan 6/28/2022 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 7/6/2022 Approved EVAN COOPER
Shower Pan 7/6/2022 Approved EVAN COOPER
Final 8/25/2022 Not Ready for Inspection JOHNNY MIRANDA
Green Building Final 8/25/2022 Not Ready for Inspection JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 8/25/2022 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 8/25/2022 Not Ready for Inspection JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Not Ready EVAN COOPER
ELECTRICAL-Final 9/6/2022 Corrections Issued EVAN COOPER
Final 9/6/2022 Corrections Issued EVAN COOPER
Green Building Final 9/6/2022 Not Ready for Inspection EVAN COOPER
HVAC-Final 9/6/2022 Corrections Issued EVAN COOPER
PLUMBING-Final 9/6/2022 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/6/2022 SGSOV Not Ready EVAN COOPER
Smoke Detectors 9/6/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Not Ready EVAN COOPER
Final 10/6/2022 Corrections Issued EVAN COOPER
Green Building Final 10/6/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved EVAN COOPER
Final 10/11/2022 OK to Issue CofO EVAN COOPER