8132 1/2 W 4TH ST 90048
Certificate Information: 8132 1/2 W 4TH ST 90048
- Application / Permit
- 22016-10000-00670
- Plan Check / Job No.
- B22LA00395
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) TWO CAR GARAGE AND REC ROOM (524) CONVERSION INTO ADU
- Permit Issued
- Issued on 4/6/2022
- Issuing Office
- Current Status
- CofO Issued on 10/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2022 | JOSEPH RAFOLS |
| Corrections Issued | 1/14/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 2/5/2022 | FERNANDO FLORES |
| Plan Check Approved | 3/22/2022 | FERNANDO FLORES |
| Issued | 4/6/2022 | APPLICANT |
| Building Plans Picked Up | 4/14/2022 | APPLICANT |
| CofO in Progress | 10/11/2022 | EVAN COOPER |
| Permit Finaled | 10/19/2022 | DANIEL ORRANTE |
| CofO Issued | 10/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2022 | STEVE MELGAR |
| Abandoned oil well | Cleared | 1/24/2022 | MENOA AGHAJANI |
| Tenant Habitability Plan | Cleared | 1/24/2022 | JORGE ALCANTAR |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 1/31/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 3/15/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/20/2022 | Corrections Issued | EVAN COOPER |
| Pre-Inspection | 4/20/2022 | Approved | EVAN COOPER |
| Pre-Inspection | 4/27/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 4/29/2022 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 5/3/2022 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 5/3/2022 | Partial Approval | EVAN COOPER |
| Sewer | 5/3/2022 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 5/4/2022 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/5/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 5/16/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 5/16/2022 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 5/16/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 5/16/2022 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 5/16/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 5/20/2022 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 5/20/2022 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 5/20/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 5/31/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 5/31/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 6/2/2022 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 6/2/2022 | Corrections Issued | MICHAEL PELHAM |
| METHANE-Rough | 6/2/2022 | Approved | MICHAEL PELHAM |
| PLUMBING-Rough | 6/2/2022 | Corrections Issued | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 6/3/2022 | Corrections Issued | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 6/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 6/9/2022 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/9/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/13/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 6/13/2022 | Approved | EVAN COOPER |
| Green Building Rough | 6/13/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 6/13/2022 | Approved | EVAN COOPER |
| Insulation | 6/13/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/13/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 6/15/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 6/28/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/28/2022 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 6/28/2022 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 7/6/2022 | Approved | EVAN COOPER |
| Shower Pan | 7/6/2022 | Approved | EVAN COOPER |
| Final | 8/25/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Final | 8/25/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 8/25/2022 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 8/25/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 8/31/2022 | SGSOV Not Ready | EVAN COOPER |
| ELECTRICAL-Final | 9/6/2022 | Corrections Issued | EVAN COOPER |
| Final | 9/6/2022 | Corrections Issued | EVAN COOPER |
| Green Building Final | 9/6/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 9/6/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 9/6/2022 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 9/6/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Not Ready | EVAN COOPER |
| Final | 10/6/2022 | Corrections Issued | EVAN COOPER |
| Green Building Final | 10/6/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Approved | EVAN COOPER |
| Final | 10/11/2022 | OK to Issue CofO | EVAN COOPER |