2560 N GLENDALE BLVD 90039
Certificate Information: 2560 N GLENDALE BLVD 90039
- Application / Permit
- 22016-10000-00500
- Plan Check / Job No.
- B21LA24489
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- ePlan Tenant Improvement and change of use of existing 940 SF bank to new Dental Clinic.
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 11/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2022 | CARLOS MONTES |
| Corrections Issued | 1/12/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 2/9/2022 | CARLOS MONTES |
| Plan Check Approved | 3/3/2022 | CARLOS MONTES |
| Issued | 3/3/2022 | APPLICANT |
| CofO in Progress | 10/17/2022 | MARK FERRARI |
| CofO Issued | 11/2/2022 | WINSTON DUNNING |
| Permit Finaled | 11/2/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/18/2022 | ANACANY HURTADO |
| Comm Cor/Mini-Mall | Cleared | 1/18/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 1/18/2022 | ANACANY HURTADO |
| Comm Cor/Mini-Mall | Cleared | 2/4/2022 | LOUIS ORTEGA |
| Comm Cor/Mini-Mall | Cleared | 2/4/2022 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | CINDY QI |
| Sewer availability | Cleared | 2/7/2022 | CINDY QI |
| Address approval | Cleared | 2/23/2022 | CINDY QI |
Contact Information
| Contractor | Garrett Construction Inc; Lic. No.: 974349-B | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/15/2022 | Approved | MARK FERRARI |
| Light Gage Steel Frame | 4/15/2022 | Partial Approval | MARK FERRARI |
| Insulation | 6/2/2022 | Approved | MARK FERRARI |
| Light Gage Steel Frame | 6/2/2022 | Partial Approval | MARK FERRARI |
| Light Gage Steel Frame | 6/6/2022 | Approved | MARK FERRARI |
| Drywall Nailing | 6/9/2022 | Approved | ERNESTO CORRAL |
| T-Bar Ceiling | 8/11/2022 | Approved | MARK FERRARI |
| Final | 9/6/2022 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/6/2022 | Approved | MARK FERRARI |
| Wood Frame | 9/6/2022 | Approved | MARK FERRARI |
| Final | 9/12/2022 | Conditional Approval | MARK FERRARI |