800 W 6TH ST 3rd Floor 90017
Certificate Information: 800 W 6TH ST 3rd Floor 90017
- Application / Permit
- 22016-10000-00493
- Plan Check / Job No.
- B22LA00324
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Upgrade Restroom and Elevator Lobby - 3rd Floor
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Current Status
- Permit Finaled on 5/10/2023
Permit Application Status History
| Submitted | 1/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2022 | JOE VO |
| Corrections Issued | 1/11/2022 | JOE VO |
| Plan Check Approved | 1/19/2022 | JOE VO |
| Issued | 5/10/2022 | APPLICANT |
| Permit Finaled | 5/8/2023 | KATY RAMIREZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Condu Corporation; Lic. No.: 297033-B | 1200 WILSHIRE BLVD STE 407 LOS ANGELES, CA 90017 |
| Engineer | Youngblood,, Charles St Denny; Lic. No.: C45031 | 556 SEGOVIA AVE SAN GABRIEL, CA 91775 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 9/9/2022 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 10/24/2022 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 10/24/2022 | Approved | TIMOTHY BUXTON |
| T-Bar Ceiling | 10/24/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 11/2/2022 | Approved | TIMOTHY BUXTON |
| Final | 3/30/2023 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 3/30/2023 | Approved | KATY RAMIREZ |
| Final | 5/8/2023 | Permit Finaled | KATY RAMIREZ |