1341 S MEADOWBROOK AVE 90019

Certificate Information: 1341 S MEADOWBROOK AVE 90019

Application / Permit
22016-10000-00380
Plan Check / Job No.
B22LA00239
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING EX 2 CAR GARAGE TO A NEW DETACHED ADU ACCESSORY DWELLING UNIT PER STATE LAW AND GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 6/29/2022
Issuing Office
Current Status
CofO Issued on 11/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2022 ZAW HAN
Corrections Issued 1/18/2022 ZAW HAN
Plan Check Approved 2/18/2022 JOSEPH RAFOLS
Building Plans Picked Up 2/22/2022 APPLICANT
Issued 6/29/2022 APPLICANT
CofO in Progress 11/21/2022 JOSE AVILA
Permit Finaled 11/29/2022 DEROLD HAUFF
CofO Issued 11/29/2022 DEROLD HAUFF
Permit Finaled 11/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/21/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/21/2022 JEANETTE VONG
Sewer availability Cleared 1/21/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 2/7/2022 AMAAN MALIK

Contact Information

Contractor Parkview Management And Development Company; Lic. No.: 909073-B 8915 S SEPULVEDA BLVD      LOS ANGELES, CA 90045
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/5/2022 Partial Approval JOSE AVILA
Underground Mechanical 7/5/2022 Partial Approval JOSE AVILA
METHANE-Rough 7/12/2022 Partial Approval ALIZAH MAYAGOITIA
Sewer 7/13/2022 Corrections Issued ALIZAH MAYAGOITIA
Deputy Methane Barrier 7/20/2022 Conditional Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 7/27/2022 Approved JOSE AVILA
Footing/Foundation/Slab 7/27/2022 Approved JOSE AVILA
METHANE-Barrier 7/27/2022 Approved JOSE AVILA
HVAC-Rough 8/31/2022 Approved JOSE AVILA
PLUMBING-Rough 8/31/2022 Approved JOSE AVILA
ELECTRICAL-Rough 9/6/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 9/7/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 9/12/2022 Approved JOSE AVILA
METHANE-Rough 9/12/2022 Approved JOSE AVILA
Deputy Wood Construction 9/14/2022 Conditional Approval JOSE AVILA
Insulation 9/14/2022 Approved JOSE AVILA
Drywall Nailing 9/15/2022 Approved JOSE AVILA
Interior/Exterior Lathing 9/15/2022 Partial Approval JOSE AVILA
Gas Test 9/19/2022 Partial Approval JOSE AVILA
Interior/Exterior Lathing 9/27/2022 Approved JOSE AVILA
ELECTRICAL-Final 10/24/2022 Corrections Issued JOSE AVILA
HVAC-Final 10/24/2022 Approved JOSE AVILA
PLUMBING-Final 10/24/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 11/2/2022 Approved JOSE AVILA
Final 11/2/2022 OK to Issue CofO JOSE AVILA
Green Building Final 11/2/2022 Approved JOSE AVILA
Green Building Rough 11/2/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/2/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 11/2/2022 Approved JOSE AVILA