3500 W 6TH ST 90020
Certificate Information: 3500 W 6TH ST 90020
- Application / Permit
- 22016-10000-00330
- Plan Check / Job No.
- B21LA22704
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Alteration to the existing framing of an existing commercial building for the framing of two new digital signs (digital signs are under separate permits)
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/4/2023
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | MINA HABIB |
| Corrections Issued | 1/6/2022 | MINA HABIB |
| Quality Review Completed | 1/6/2022 | FARUK SEZER |
| Building Plans Picked Up | 1/10/2022 | APPLICANT |
| Applicant returned to address corrections | 3/14/2022 | MINA HABIB |
| Applicant returned to address corrections | 5/3/2022 | MINA HABIB |
| Applicant returned to address corrections | 5/11/2022 | MINA HABIB |
| Applicant returned to address corrections | 5/16/2022 | MINA HABIB |
| Plan Check Approved | 5/25/2022 | MINA HABIB |
| Issued | 6/23/2022 | APPLICANT |
| Permit Finaled | 12/4/2023 | RONALD JIMENEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2022 | WALLIE JONG |
| Historic Resource Verification | Cleared | 1/19/2022 | MAX LODER |
| DAS Clearance | Cleared | 2/11/2022 | MINA HABIB |
| Redevelopment Project Area | Cleared | 2/15/2022 | DAVID URITA |
| Building over 36-ft | Cleared | 5/12/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Schroeder,, Mark; Lic. No.: S4110 | 16969 VON KARMAN AVE 240 IRVINE, CA 92606 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/6/2023 | Approved | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/12/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Steel/Welding | 10/13/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Steel/Welding | 10/16/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Steel/Welding | 10/17/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Steel/Welding | 10/18/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Steel/Welding | 10/19/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Steel/Welding | 10/20/2023 | Conditional Approval | RONALD JIMENEZ |
| Structural Steel Frame | 10/26/2023 | Partial Approval | MARTIN TAVITIAN |
| Deputy Steel/Welding | 11/13/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Steel/Welding | 11/15/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Steel/Welding | 11/17/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Steel/Welding | 11/28/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Steel/Welding | 11/29/2023 | Conditional Approval | RONALD JIMENEZ |
| Final | 12/1/2023 | Conditional Approval | RONALD JIMENEZ |
| Structural Steel Frame | 12/1/2023 | Approved | RONALD JIMENEZ |
| Final | 12/4/2023 | Permit Finaled | RONALD JIMENEZ |
| Smoke Detectors | 12/4/2023 | Approved | RONALD JIMENEZ |