26650 S WESTERN AVE C 90710
Certificate Information: 26650 S WESTERN AVE C 90710
- Application / Permit
- 22016-10000-00308
- Plan Check / Job No.
- B22LA00185
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Bank
- Work Description
- ePlan, Change of use from restaurant/retail to bank. Construction of new Non-Structural partitions, and new finishes.
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Current Status
- CofO Issued on 8/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2022 | LARRY LEE |
| Corrections Issued | 1/7/2022 | LARRY LEE |
| Applicant returned to address corrections | 2/8/2022 | LARRY LEE |
| Applicant returned to address corrections | 3/10/2022 | LARRY LEE |
| Applicant returned to address corrections | 4/14/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 5/13/2022 | MICHAEL LOPEZ |
| Issued | 5/16/2022 | APPLICANT |
| CofO in Progress | 8/10/2022 | DAVID TSAU |
| CofO Issued | 8/10/2022 | DAVID TSAU |
| Permit Finaled | 8/10/2022 | DAVID TSAU |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/24/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 2/24/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 2/24/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 2/24/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 2/24/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 2/24/2022 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2022 | HUGO LOPEZ |
| Sewer availability | Cleared | 4/6/2022 | HUGO LOPEZ |
| Comm Cor/Mini-Mall | Cleared | 5/3/2022 | MIGUEL GAMBOA |
Contact Information
| Architect | Odle,, Terry Wynn; Lic. No.: NA21913 | , |
| Contractor | Tenant Works Inc; Lic. No.: 738903-B | , |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 5/19/2022 | Partial Approval | JOEY BUCHANAN |
| Insulation | 5/26/2022 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 6/3/2022 | Approved | JOEY BUCHANAN |
| T-Bar Ceiling | 6/23/2022 | Conditional Approval | JOEY BUCHANAN |
| Final | 8/8/2022 | OK to Issue CofO | DAVID TSAU |
| Green Building Final | 8/8/2022 | Approved | DAVID TSAU |
| Green Building Rough | 8/8/2022 | Approved | DAVID TSAU |
| SGSOV-Seismic Gas S/O Valve | 8/8/2022 | SGSOV No Gas | DAVID TSAU |
| Smoke Detectors | 8/8/2022 | Approved | DAVID TSAU |
| Wood Frame | 8/8/2022 | Approved | DAVID TSAU |
| Special/Order Compliance | 8/9/2022 | Partial Inspection | DAVID TSAU |