1965 1/2 S PREUSS ROAD 90035
Certificate Information: 1965 1/2 S PREUSS ROAD 90035
- Application / Permit
- 22016-10000-00239
- Plan Check / Job No.
- B22LA00158
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF (E) GARAGE WITH AN ADDITION TO A DETACHED ADU PER ORDINANCE
- Permit Issued
- Issued on 4/20/2022
- Issuing Office
- Current Status
- CofO Issued on 6/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2022 | CARLOS MONTES |
| Corrections Issued | 1/6/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 1/21/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 1/27/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 2/15/2022 | CARLOS MONTES |
| Plan Check Approved | 3/10/2022 | CARLOS MONTES |
| Issued | 4/20/2022 | APPLICANT |
| CofO in Progress | 6/9/2023 | JEREMY TODD |
| Permit Finaled | 6/26/2023 | DANIEL ORRANTE |
| CofO Issued | 6/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 1/11/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 1/19/2022 | JEANETTE VONG |
| Tenant Habitability Plan | Cleared | 1/20/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Areio Inc; Lic. No.: 997015-B | 73 NIGHTHAWK IRVINE, CA 92604 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/6/2022 | Approved | EVAN COOPER |
| Pre-Inspection | 11/8/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 2/23/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 2/23/2023 | Approved | JEREMY TODD |
| Deputy Drilled-In Anchors | 2/28/2023 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 4/3/2023 | Approved | JEREMY TODD |
| Insulation | 4/3/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 4/4/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 4/5/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 4/5/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/19/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 5/10/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 5/10/2023 | Approved | JEREMY TODD |
| Final | 5/10/2023 | Corrections Issued | JEREMY TODD |
| Green Building Final | 5/10/2023 | Approved | JEREMY TODD |
| Green Building Rough | 5/10/2023 | Approved | JEREMY TODD |
| HVAC-Final | 5/10/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 5/10/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Approved | JEREMY TODD |
| Smoke Detectors | 5/10/2023 | Approved | JEREMY TODD |
| Final | 6/9/2023 | OK to Issue CofO | JEREMY TODD |