6324 S 8TH AVE 90043
Certificate Information: 6324 S 8TH AVE 90043
- Application / Permit
- 22014-40000-06373
- Plan Check / Job No.
- B22SP00128
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PORTION OF (E) GARAGE WALL AND FOUNDATION TO REMAIN AS STORAGE WITH PROPOSED NEW ADDITION OF 1-STORY A.D.U. PER ORDINANCE AT REAR OF LOT. CONSTRUCTION PER W.F.P.P. WITH BRACED WALL LENGTH OPTION.
- Permit Issued
- Issued on 5/6/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/5/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 1/17/2023 | APPLICANT |
| Plan Check Approved | 3/8/2024 | MINA HABILI |
| Issued | 5/6/2024 | APPLICANT |
| CofO in Progress | 7/17/2025 | MICHAEL LEWIS |
| Permit Finaled | 7/18/2025 | DEROLD HAUFF |
| CofO Issued | 7/18/2025 | DEROLD HAUFF |
| Permit Finaled | 7/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2023 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 11/27/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/11/2024 | LUIS CRUZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2024 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 2/13/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 2/13/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/2/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 12/23/2024 | Partial Approval | AMIR NAZARIAN |
| Insulation | 12/27/2024 | Partial Approval | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2024 | Corrections Issued | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2025 | Partial Approval | AMIR NAZARIAN |
| ELECTRICAL-Rough | 2/11/2025 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 2/11/2025 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 2/11/2025 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/19/2025 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 2/19/2025 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 2/19/2025 | Approved | MICHAEL LEWIS |
| Insulation | 2/25/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 2/25/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 2/25/2025 | Partial Approval | ANTHONY RAMOS |
| Green Building Rough | 2/26/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 3/5/2025 | Corrections Issued | ANTHONY RAMOS |
| Sewer | 3/5/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 3/6/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 3/21/2025 | Approved | MICHAEL LEWIS |
| Gas Test | 4/15/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 6/13/2025 | Approved | WAYNE REGESTER |
| Final | 6/13/2025 | Conditional Approval | WAYNE REGESTER |
| Footing/Foundation/Slab | 6/13/2025 | Approved | WAYNE REGESTER |
| Green Building Final | 6/13/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Approved | WAYNE REGESTER |
| Service/Power Release | 6/13/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 6/13/2025 | Approved | WAYNE REGESTER |
| Final | 7/17/2025 | OK to Issue CofO | WAYNE REGESTER |