21128 S HARVARD BLVD 90501

Certificate Information: 21128 S HARVARD BLVD 90501

Application / Permit
22014-40000-05275
Plan Check / Job No.
B22SP00040
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO A.D.U. PER STATE LAW. INCLUDES NEW LAUNDRY ADDITION AT REAR OF BLDG.
Permit Issued
Issued on 12/27/2022
Issuing Office
San Pedro
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2022 APPLICANT
Assigned to Plan Check Engineer 10/25/2022 LAWRENCE QUIRANTE
Corrections Issued 10/25/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 12/13/2022 LAWRENCE QUIRANTE
Plan Check Approved 12/22/2022 LAWRENCE QUIRANTE
Issued 12/27/2022 APPLICANT
CofO in Progress 2/16/2024 EUGENE CASSIDY
Permit Finaled 2/22/2024 ANSON MAGLASANG
CofO Issued 2/22/2024 ANSON MAGLASANG
Permit Finaled 2/22/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 12/5/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 12/5/2022 ERIK BEASLEY
Sewer availability Cleared 12/27/2022 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Liu,, Hue C; Lic. No.: C66754 10732 LA BATISTA AVENUE      FOUNTAIN VALLEY, CA 92708

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/4/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 1/4/2023 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 1/4/2023 Corrections Issued EUGENE CASSIDY
Green Building Rough 1/4/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 1/4/2023 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 1/4/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 1/9/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 1/9/2023 Corrections Issued EUGENE CASSIDY
Green Building Rough 1/9/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 1/9/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 1/11/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 1/11/2023 Corrections Issued EUGENE CASSIDY
Deputy Drilled-In Anchors 1/12/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 1/13/2023 Approved EUGENE CASSIDY
Footing/Foundation/Slab 1/13/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 1/20/2023 Corrections Issued EUGENE CASSIDY
Green Building Rough 1/20/2023 Not Ready for Inspection EUGENE CASSIDY
Insulation 1/20/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 1/24/2023 Approved EUGENE CASSIDY
Green Building Rough 1/24/2023 Approved EUGENE CASSIDY
Insulation 1/24/2023 Approved EUGENE CASSIDY
Drywall Nailing 2/1/2023 Corrections Issued EUGENE CASSIDY
Drywall Nailing 2/3/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/3/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 2/3/2023 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 3/9/2023 Corrections Issued EUGENE CASSIDY
Final 3/13/2023 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 3/13/2023 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 3/17/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Final 3/22/2023 Approved EUGENE CASSIDY
Special/Order Compliance 3/22/2023 Corrections Issued EUGENE CASSIDY
Final 3/24/2023 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 3/24/2023 Approved EUGENE CASSIDY
Final 2/13/2024 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Approved EUGENE CASSIDY
ELECTRICAL-Final 2/15/2024 Approved EUGENE CASSIDY
Final 2/15/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 2/15/2024 Approved EUGENE CASSIDY
PLUMBING-Final 2/15/2024 Approved EUGENE CASSIDY