2361 S KELTON AVE 90064

Certificate Information: 2361 S KELTON AVE 90064

Application / Permit
22014-30001-00032
Plan Check / Job No.
B23WL01030
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental ref to permit # 22014-30000-00032 to revise the scope of work from major remodel and 2nd floor addition with new attached garage to new 2-story S.F.D. whith attached garage.
Permit Issued
Issued on 8/17/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 11/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2023 APPLICANT
Assigned to Plan Check Engineer 4/19/2023 HOOMAN HAJIZADEH
Corrections Issued 4/27/2023 HOOMAN HAJIZADEH
Building Plans Picked Up 5/1/2023 APPLICANT
Plan Check Approved 8/15/2023 HOOMAN HAJIZADEH
Issued 8/17/2023 APPLICANT
Permit Finaled 11/25/2024 BOBBY KEY

Permit Application Clearance Information

Address approval Cleared 6/26/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 6/27/2023 JASON NG
Hydrant and Access approval Cleared 7/13/2023 LAVEON RIDER

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Namdar,, Mansour Tom; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/25/2023 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 12/12/2023 Corrections Issued JESUS PINEDA
PLUMBING-Rough 12/12/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 12/18/2023 Partial Approval JESUS PINEDA
Underground Mechanical 12/18/2023 Corrections Issued JESUS PINEDA
Underground Mechanical 12/20/2023 Corrections Issued HERBERT GIRON
Underground Mechanical 1/16/2024 No Access for Inspection CARLOS MATAMOROS
PLUMBING-Rough 1/31/2024 Partial Approval JESUS PINEDA
Sewer 1/31/2024 Approved JESUS PINEDA
Footing/Foundation/Slab 3/6/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Approved JESUS PINEDA
HVAC-Rough 6/11/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 6/11/2024 Approved JESUS PINEDA
Shower Pan 6/11/2024 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 6/13/2024 Partial Approval JESUS PINEDA
Shower Pan 6/13/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 7/1/2024 Approved JESUS PINEDA
PLUMBING-Rough 7/1/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 7/3/2024 Approved MEL KHACHATOURIAN
Wood Frame 7/3/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 7/8/2024 Conditional Approval KIRK SANDERS
Insulation 7/19/2024 Corrections Issued JESUS PINEDA
Drywall Nailing 7/31/2024 Approved JESUS PINEDA
Green Building Rough 7/31/2024 Approved JESUS PINEDA
Insulation 7/31/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 7/31/2024 Approved JESUS PINEDA
ELECTRICAL-Final 10/18/2024 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 10/22/2024 Approved DANIEL VERA
ELECTRICAL-Final 10/30/2024 Approved DANIEL VERA
PLUMBING-Final 10/30/2024 Approved DANIEL VERA
Service/Power Release 10/30/2024 Approved DANIEL VERA