1349 S ALLENFORD AVE 90049
Certificate Information: 1349 S ALLENFORD AVE 90049
- Application / Permit
- 22014-30000-06345
- Plan Check / Job No.
- B22WL04667
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st and 2nd floor addition to a (e) 1-story S.F.D. w/ trellis rear patio cover *** 1 of 2 ***
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2023 | YASHAR EMAMI |
| Corrections Issued | 1/15/2023 | YASHAR EMAMI |
| Quality Review Completed | 1/19/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 2/16/2023 | APPLICANT |
| Applicant returned to address corrections | 8/9/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 8/21/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 8/30/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 9/6/2023 | YASHAR EMAMI |
| Plan Check Approved | 9/18/2023 | YASHAR EMAMI |
| Issued | 9/19/2023 | APPLICANT |
| CofO in Progress | 3/6/2025 | KENNETH NAGLE |
| CofO Issued | 3/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2023 | DINAH GARIN |
| Permit | Cleared | 4/21/2023 | DINAH GARIN |
| Low Impact Development | Cleared | 6/21/2023 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/6/2023 | LIAM ODONOVAN |
| Hydrant and Access approval | Cleared | 7/12/2023 | LAVEON RIDER |
| Trees in Parkway | Cleared | 7/19/2023 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 9/6/2023 | YASHAR EMAMI |
| Grading Pre-Inspection | Cleared | 9/6/2023 | YASHAR EMAMI |
Contact Information
| Contractor | Landmark Construction Group Inc; Lic. No.: 732270-B | 275 S ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/20/2023 | Approved | TEMISTOCLES CAAL |
| Sewer | 11/20/2023 | Approved | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 12/12/2023 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 1/11/2024 | Approved | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 1/26/2024 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 2/12/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 2/12/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/8/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Approved | MICHAEL PELHAM |
| HVAC-Rough | 5/15/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 5/23/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 6/3/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/10/2024 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/12/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 6/12/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 6/12/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 6/17/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 6/24/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/19/2024 | Approved | EVAN COOPER |
| Sewer | 9/19/2024 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 9/19/2024 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/23/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 10/28/2024 | Partial Approval | JESUS RODRIGUEZ |
| Gas Test | 12/4/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/23/2024 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 12/26/2024 | Approved | KENNETH NAGLE |
| HVAC-Final | 1/28/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Final | 1/28/2025 | Approved | JESUS RODRIGUEZ |
| Final | 2/12/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 2/12/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 2/12/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 2/12/2025 | Approved | JESUS RODRIGUEZ |
| Final | 3/6/2025 | OK to Issue CofO | KENNETH NAGLE |