14611 W CAREY ST 90272

Certificate Information: 14611 W CAREY ST 90272

Application / Permit
22014-30000-06320
Plan Check / Job No.
B22WL04655
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ADU above existing detached garage w/ a roof deck per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 9/18/2023
Issuing Office
West Los Angeles
Current Status
Issued on 9/18/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 1/11/2023 HOOMAN HAJIZADEH
Corrections Issued 1/20/2023 HOOMAN HAJIZADEH
Quality Review Completed 1/23/2023 CHIHARU SUZUKI
Building Plans Picked Up 1/27/2023 APPLICANT
Applicant returned to address corrections 5/19/2023 HOOMAN HAJIZADEH
Plan Check Approved 9/18/2023 HOOMAN HAJIZADEH
Issued 9/18/2023 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 2/23/2023 KENTON TRINH
Address approval Cleared 2/27/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 3/6/2023 JASON NG
Sewer availability Cleared 3/6/2023 JASON NG
Grading Pre-Inspection Cleared 3/8/2023 KIRK LINKLATER
Hydrant and Access approval Cleared 5/4/2023 LAVEON RIDER
Low Impact Development Cleared 6/13/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/7/2023 KATHLEEN LEE
Construction within easement Cleared 8/17/2023 RIDWAN HARDY

Contact Information

Contractor We Build Green Inc; Lic. No.: 1073455-B 24306 GILMORE ST      WEST HILLS, CA 91307
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Engineer Manepalli,, Pavan S; Lic. No.: C72416 15742 57TH PLACE NORTH      PLYMOUTH, MN 55446

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/17/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/17/2023 Not Ready for Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 10/20/2023 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/1/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 11/28/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval MICHAEL PELHAM
ELECTRICAL-Rough 2/14/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Corrections Issued EVAN COOPER
Green Building Rough 2/14/2024 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 2/14/2024 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 4/3/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 4/3/2024 Approved ARAM AVEDISIAN
HVAC-Rough 4/3/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 4/3/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 4/8/2024 Approved ARAM AVEDISIAN
Green Building Rough 4/8/2024 Approved ARAM AVEDISIAN
HVAC-Rough 4/8/2024 Approved ARAM AVEDISIAN
Insulation 4/10/2024 Corrections Issued KENNETH NAGLE
Interior/Exterior Lathing 7/22/2024 Partial Approval ARAM AVEDISIAN
Insulation 9/19/2024 Corrections Issued JESUS RODRIGUEZ
Shower Pan 9/19/2024 Corrections Issued JESUS RODRIGUEZ
Insulation 9/24/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 10/2/2024 Corrections Issued JESUS RODRIGUEZ
Special/Order Compliance 10/2/2024 Corrections Issued JESUS RODRIGUEZ