3343 1/2 E MACEO ST 90065
Certificate Information: 3343 1/2 E MACEO ST 90065
- Application / Permit
- 22014-30000-06251
- Plan Check / Job No.
- B22WL04634
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition of 188 sf and interior remodel for (E) Single Family Dwelling at rear of the lot
- Permit Issued
- Issued on 5/22/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2023 | EDWIN ESPIN |
| Corrections Issued | 1/6/2023 | EDWIN ESPIN |
| Building Plans Picked Up | 1/10/2023 | APPLICANT |
| Applicant returned to address corrections | 5/10/2023 | EDWIN ESPIN |
| Plan Check Approved | 5/18/2023 | EDWIN ESPIN |
| Issued | 5/22/2023 | APPLICANT |
| CofO in Progress | 3/13/2024 | OSVALDO PARAMO |
| CofO Issued | 3/19/2024 | DEROLD HAUFF |
| Permit Finaled | 3/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/3/2023 | ISMAEL HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 2/10/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2023 | ADRIAN SANCHEZ |
| ZI | Cleared | 4/18/2023 | NICOLE SANCHEZ |
| Grading Pre-Inspection | Cleared | 5/10/2023 | EDWIN ESPIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lobnan,, Essam; Lic. No.: C78053 | PO BOX 64373 LOS ANGELES, CA 90064 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/22/2023 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/28/2023 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/6/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 8/24/2023 | Conditional Approval | OSVALDO PARAMO |
| Deck | 9/6/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 9/6/2023 | Conditional Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 9/6/2023 | Corrections Issued | OSVALDO PARAMO |
| Wood Frame | 9/6/2023 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 9/13/2023 | Approved | OSVALDO PARAMO |
| HVAC-Final | 9/13/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 9/21/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 9/21/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/21/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 9/21/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 9/26/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/26/2023 | Approved | OSVALDO PARAMO |
| Shower Pan | 9/26/2023 | Approved | OSVALDO PARAMO |
| Insulation | 9/29/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 10/16/2023 | Approved | OSVALDO PARAMO |
| Final | 11/27/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 11/27/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 11/27/2023 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 11/27/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 2/7/2024 | Corrections Issued | OSVALDO PARAMO |
| Smoke Detectors | 2/7/2024 | Approved | OSVALDO PARAMO |
| Final | 3/1/2024 | OK to Issue CofO | OSVALDO PARAMO |