11351-11353 W CHENAULT ST 90049

Certificate Information: 11351-11353 W CHENAULT ST 90049

Application / Permit
22014-30000-06234
Plan Check / Job No.
B22WL04621
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel and 2nd story addition to existing SFD and convert portion of SFD to ADU per ordinance.
Permit Issued
Issued on 1/12/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Assigned to Plan Check Engineer 1/11/2023 KAVIAN REFAHI
Corrections Issued 1/18/2023 KAVIAN REFAHI
Quality Review Completed 1/20/2023 CHIHARU SUZUKI
Building Plans Picked Up 2/16/2023 APPLICANT
Applicant returned to address corrections 11/30/2023 KAVIAN REFAHI
Plan Check Approved 1/12/2024 KAVIAN REFAHI
Issued 1/12/2024 APPLICANT
CofO in Progress 3/14/2025 CARLOS MATAMOROS
CofO Issued 3/15/2025 RICHARD STEINBACH
Permit Finaled 3/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 8/24/2023 JASON CHAN
ZA Case Cleared 8/24/2023 JASON CHAN
Low Impact Development Cleared 9/6/2023 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 9/8/2023 DINAH GARIN
Sewer availability Cleared 9/8/2023 DINAH GARIN
Roof/Waste drainage to street Cleared 9/15/2023 ANTHONY MAINEZ
GPI Written Notices Cleared 11/30/2023 KAVIAN REFAHI
Grading Pre-Inspection Cleared 11/30/2023 KAVIAN REFAHI
Address approval Cleared 12/11/2023 VLADIMIR ARUTYUNYAN
Specific Plan Cleared 12/11/2023 ALESSANDRO MERCURI

Contact Information

Contractor G S Construction; Lic. No.: 540685-B 17116 HALSTED ST      NORTHRIDGE, CA 91325
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/15/2024 Not Ready for Inspection CARLOS MATAMOROS
METHANE-Barrier 2/15/2024 Not Ready for Inspection CARLOS MATAMOROS
METHANE-Subgrade 2/15/2024 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 5/10/2024 Corrections Issued CARLOS MATAMOROS
METHANE-Barrier 5/10/2024 Approved CARLOS MATAMOROS
METHANE-Subgrade 5/10/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 5/14/2024 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 5/17/2024 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 5/31/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 8/14/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Approved CARLOS MATAMOROS
Green Building Rough 8/14/2024 Approved CARLOS MATAMOROS
HVAC-Rough 8/14/2024 Corrections Issued CARLOS MATAMOROS
MERV13>=Rough 8/14/2024 Approved CARLOS MATAMOROS
METHANE-Rough 8/14/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 8/19/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 8/19/2024 No Access for Inspection CARLOS MATAMOROS
HVAC-Rough 8/19/2024 No Access for Inspection CARLOS MATAMOROS
PLUMBING-Rough 8/19/2024 No Access for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 8/20/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 8/20/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Approved CARLOS MATAMOROS
Green Building Rough 8/20/2024 Approved CARLOS MATAMOROS
HVAC-Rough 8/20/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 8/20/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Approved MEL KHACHATOURIAN
Insulation 8/26/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 8/26/2024 Partial Approval MEL KHACHATOURIAN
Shower Pan 8/26/2024 Not Ready for Inspection MEL KHACHATOURIAN
Drywall Nailing 8/30/2024 Approved CARLOS MATAMOROS
Shower Pan 8/30/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 10/2/2024 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 10/4/2024 Approved CARLOS MATAMOROS
Gas Test 10/9/2024 Approved CARLOS MATAMOROS
HVAC-Final 1/17/2025 Corrections Issued CARLOS MATAMOROS
Service/Power Release 1/17/2025 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 1/23/2025 Approved CARLOS MATAMOROS
HVAC-Final 1/23/2025 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 1/23/2025 Approved CARLOS MATAMOROS
Service/Power Release 1/23/2025 Approved CARLOS MATAMOROS
Final 3/13/2025 OK to Issue CofO CARLOS MATAMOROS
Footing/Foundation/Slab 3/13/2025 Approved CARLOS MATAMOROS
Green Building Final 3/13/2025 Approved CARLOS MATAMOROS
HVAC-Final 3/13/2025 Approved CARLOS MATAMOROS
MERV13>=Final 3/13/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/13/2025 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 3/13/2025 Approved CARLOS MATAMOROS