584 W 10TH ST 90731
Certificate Information: 584 W 10TH ST 90731
- Application / Permit
- 22014-30000-06152
- Plan Check / Job No.
- B22WL04591
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- proposed new 370 sf covered patio per ladbs standard plan "COMPLY WITH DEPARTMENT ORDER effective date 11/28/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 973924. **see comments**
- Permit Issued
- Issued on 1/3/2023
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 6/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2022 | AMY GUEVARRA |
| Corrections Issued | 12/20/2022 | AMY GUEVARRA |
| Applicant returned to address corrections | 12/23/2022 | AMY GUEVARRA |
| Plan Check Approved | 1/3/2023 | LAWRENCE QUIRANTE |
| Issued | 1/3/2023 | APPLICANT |
| CofO in Progress | 4/6/2023 | PAUL BECKER |
| Permit Finaled | 6/5/2023 | BRUCE TODD |
| CofO Issued | 6/5/2023 | BRUCE TODD |
| Permit Finaled | 6/5/2023 | BRUCE TODD |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2022 | JASON NG |
| Roof/Waste drainage to street | Cleared | 12/20/2022 | JASON NG |
| Historic Resource Verification | Cleared | 12/29/2022 | DAVID URITA |
| Redevelopment Project Area | Cleared | 12/29/2022 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/24/2023 | Corrections Issued | ANDREW BEELI |
| Final | 3/7/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Footing/Foundation/Slab | 3/7/2023 | Approved | BRIAN CHRISTIAN |
| Green Building Final | 3/7/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Green Building Rough | 3/7/2023 | Approved | BRIAN CHRISTIAN |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Approved | BRIAN CHRISTIAN |
| Smoke Detectors | 3/7/2023 | Approved | BRIAN CHRISTIAN |
| Wood Frame | 3/7/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Final | 3/24/2023 | Conditional Approval | PAUL BECKER |
| Green Building Final | 3/24/2023 | Approved | PAUL BECKER |
| Wood Frame | 3/24/2023 | Approved | PAUL BECKER |
| Final | 4/6/2023 | OK to Issue CofO | PAUL BECKER |