5966 W 85TH PL 90045

Certificate Information: 5966 W 85TH PL 90045

Application / Permit
22014-30000-06002
Plan Check / Job No.
B22WL04489
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Building Addition: - proposed interior remodeling: removal of bearing and non-bearing walls - convert (e) covered patio to (n) laundry room + (n) addition to laundry room. - adding (n) storage area -kitchen remodel
Permit Issued
Issued on 2/28/2023
Issuing Office
West Los Angeles
Current Status
CofO Corrected on 1/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2022 APPLICANT
Assigned to Plan Check Engineer 12/12/2022 RICHARD GARCIA
Corrections Issued 12/13/2022 RICHARD GARCIA
Building Plans Picked Up 12/16/2022 APPLICANT
Applicant returned to address corrections 1/31/2023 JOHNPAUL ISIP
Plan Check Approved 2/21/2023 RICHARD GARCIA
Issued 2/28/2023 APPLICANT
CofO in Progress 11/8/2023 BOBBY KEY
CofO Issued-Status Void 11/14/2023 DANIEL ORRANTE
Permit Finaled-Status Void 11/14/2023 DANIEL ORRANTE
Re-Activate Permit 1/22/2024 DANIEL ORRANTE
Permit Finaled 1/22/2024 DANIEL ORRANTE
CofO Corrected 1/22/2024 DANIEL ORRANTE
Permit Finaled 1/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Tenant Habitability Plan Cleared 12/29/2022 RICARDO BOHORQUEZ
Roof/Waste drainage to street Cleared 1/19/2023 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 1/25/2023 JENSON LEE
Specific Plan Cleared 2/15/2023 JOSHUA JONES

Contact Information

Contractor Owner-Builder       ,
Engineer Cattan,, Christian George; Lic. No.: C82566 8444 OWENSMOUTH AVE      CANOGA PARK, CA 91304

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/2/2023 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 6/2/2023 Corrections Issued BOBBY KEY
Green Building Rough 6/2/2023 Not Ready for Inspection BOBBY KEY
Rough-Elec/Plmb/HVAC 6/2/2023 Not Ready for Inspection BOBBY KEY
Wood Frame 6/2/2023 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 6/27/2023 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 6/27/2023 Not Ready for Inspection BOBBY KEY
Green Building Rough 6/27/2023 Not Ready for Inspection BOBBY KEY
Rough-Elec/Plmb/HVAC 6/27/2023 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 8/1/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 8/25/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 8/25/2023 Approved BOBBY KEY
Insulation 9/6/2023 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 9/6/2023 Approved BOBBY KEY
Drywall Nailing 9/11/2023 Approved RICHARD STEINBACH
ELECTRICAL-Final 9/11/2023 Not Ready for Inspection RICHARD STEINBACH
Insulation 9/11/2023 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 9/15/2023 Approved BOBBY KEY
ELECTRICAL-Final 9/15/2023 Approved BOBBY KEY
Final 9/15/2023 Corrections Issued BOBBY KEY
Green Building Final 9/15/2023 Approved BOBBY KEY
Green Building Rough 9/15/2023 Approved BOBBY KEY
HVAC-Final 9/15/2023 Approved BOBBY KEY
PLUMBING-Final 9/15/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/15/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 9/15/2023 Approved BOBBY KEY
Final 10/30/2023 Corrections Issued BOBBY KEY
Final 11/8/2023 OK to Issue CofO BOBBY KEY