2531 S MIDVALE AVE 90064

Certificate Information: 2531 S MIDVALE AVE 90064

Application / Permit
22014-30000-05473
Plan Check / Job No.
B22WL04120
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition (396 sf) to (e) 2-story SFD (1,987 sf) to extend the living room at first floor (176 sf) and add a master bedroom (220 sf) at 2nd floor
Permit Issued
Issued on 1/12/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 REZA HAGHIGHAT
Corrections Issued 11/13/2022 REZA HAGHIGHAT
Quality Review Completed 11/26/2022 KAVIAN REFAHI
Building Plans Picked Up 11/28/2022 APPLICANT
Plan Check Approved 1/12/2023 REZA HAGHIGHAT
Issued 1/12/2023 APPLICANT
CofO in Progress 4/25/2023 MICHAEL PELHAM
Permit Finaled 4/25/2023 DANIEL ORRANTE
CofO Issued 4/25/2023 DANIEL ORRANTE
Permit Finaled 4/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/22/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 11/22/2022 DINAH GARIN
Sewer availability Cleared 11/22/2022 DINAH GARIN
ZA Case Cleared 11/28/2022 DALIA MOKAYED
Grading Pre-Inspection Cleared 1/12/2023 REZA HAGHIGHAT

Contact Information

Contractor Eurocon Group Inc; Lic. No.: 708010-B 923 HILTS AVE      LOS ANGELES, CA 90024
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/6/2023 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 2/7/2023 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/13/2023 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Partial Approval JOHNNY MIRANDA
Wood Frame 2/16/2023 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 2/27/2023 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 2/27/2023 Approved JOHNNY MIRANDA
HVAC-Rough 2/27/2023 Approved JOHNNY MIRANDA
Insulation 2/28/2023 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 3/2/2023 Approved JOHNNY MIRANDA
Drywall Nailing 3/2/2023 Approved JOHNNY MIRANDA
Green Building Rough 3/2/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 3/2/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Final 4/13/2023 Approved JOHNNY MIRANDA
Final 4/13/2023 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 4/13/2023 Approved JOHNNY MIRANDA
Green Building Final 4/13/2023 Approved JOHNNY MIRANDA
HVAC-Final 4/13/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 4/13/2023 Approved JOHNNY MIRANDA
Final 4/25/2023 OK to Issue CofO MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 4/25/2023 SGSOV Approved MICHAEL PELHAM