2533 S MIDVALE AVE 90064

Certificate Information: 2533 S MIDVALE AVE 90064

Application / Permit
22014-30000-05472
Plan Check / Job No.
B22WL04120
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) det. 2-car garage to an ADU (360 sf) per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 1/12/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 REZA HAGHIGHAT
Corrections Issued 11/13/2022 REZA HAGHIGHAT
Quality Review Completed 11/26/2022 KAVIAN REFAHI
Building Plans Picked Up 11/28/2022 APPLICANT
Plan Check Approved 1/12/2023 REZA HAGHIGHAT
Issued 1/12/2023 APPLICANT
CofO in Progress 4/25/2023 MICHAEL PELHAM
Permit Finaled 4/25/2023 DANIEL ORRANTE
CofO Issued 4/25/2023 DANIEL ORRANTE
Permit Finaled 4/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/22/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/22/2022 DINAH GARIN
Sewer availability Cleared 11/22/2022 DINAH GARIN
ZA Case Cleared 11/28/2022 DALIA MOKAYED
Miscellaneous Cleared 12/19/2022 SAUL GARCIA
Specific Plan Cleared 1/3/2023 ROBERT SANCHEZ
Hydrant and Access approval Cleared 1/9/2023 GILBERT URREA
Grading Pre-Inspection Cleared 1/12/2023 REZA HAGHIGHAT

Contact Information

Contractor Eurocon Group Inc; Lic. No.: 708010-B 923 HILTS AVE      LOS ANGELES, CA 90024
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/3/2023 Approved JOHNNY MIRANDA
PLUMBING-Rough 2/21/2023 Partial Approval JOHNNY MIRANDA
Underground Mechanical 2/21/2023 Partial Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 2/27/2023 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 2/27/2023 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 3/2/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 3/9/2023 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 3/9/2023 Corrections Issued JOHNNY MIRANDA
Wood Frame 3/9/2023 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 3/10/2023 Approved JOHNNY MIRANDA
Insulation 3/10/2023 Approved JOHNNY MIRANDA
PLUMBING-Rough 3/10/2023 Conditional Approval JOHNNY MIRANDA
Shower Pan 3/10/2023 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 3/13/2023 Partial Approval ASHLEY THOMPSON
Drywall Nailing 3/14/2023 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/14/2023 Approved JOHNNY MIRANDA
HVAC-Rough 3/15/2023 Approved JOHNNY MIRANDA
Drywall Nailing 3/17/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 3/17/2023 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 3/20/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 3/20/2023 Partial Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 4/13/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Final 4/13/2023 Approved JOHNNY MIRANDA
Final 4/13/2023 Corrections Issued JOHNNY MIRANDA
Green Building Final 4/13/2023 Approved JOHNNY MIRANDA
Green Building Rough 4/13/2023 Approved JOHNNY MIRANDA
HVAC-Final 4/13/2023 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 4/13/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 4/13/2023 Approved JOHNNY MIRANDA
Final 4/21/2023 Conditional Approval MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved MICHAEL PELHAM