2315 S SPAULDING AVE 90016

Certificate Information: 2315 S SPAULDING AVE 90016

Application / Permit
22014-30000-05428
Plan Check / Job No.
B22WL04079
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2-story addition (494 sf) and conversion of (e) det. garage (441) w./ rec-room (441 sf) above to a 2-story ADU (1,160 sf) w./ att. storage room at 1st floor (216 sf) per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 4/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 REZA HAGHIGHAT
Corrections Issued 11/28/2022 REZA HAGHIGHAT
Quality Review Completed 12/1/2022 CHIHARU SUZUKI
Building Plans Picked Up 12/2/2022 APPLICANT
Applicant returned to address corrections 1/18/2023 REZA HAGHIGHAT
Plan Check Approved 4/6/2023 REZA HAGHIGHAT
Issued 4/17/2023 APPLICANT
CofO in Progress 1/31/2025 ARTHUR NEGRETE
Permit Finaled 2/14/2025 DEROLD HAUFF
CofO Issued 2/14/2025 DEROLD HAUFF
Permit Finaled 2/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/9/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 12/9/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/12/2022 TREVOR QUAN
Sewer availability Cleared 12/12/2022 TREVOR QUAN
Construction near power lines Cleared 3/29/2023 RIDWAN HARDY

Contact Information

Contractor California Designers Remodeling Inc; Lic. No.: 946160-B 14359 ADDISON STREET #101      SHERMAN OAKS, CA 91423
Engineer Alferez,, Vicente Narvaez; Lic. No.: C53875 460 E CARSON PLAZA DR STE 212      CARSON, CA 90746

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2023 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 5/23/2023 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 6/9/2023 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/23/2023 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 7/3/2023 Partial Approval JOSE AVILA
Footing/Foundation/Slab 7/26/2023 Corrections Issued CALEB MEISTER
Excavation/Setback/Form/Re-Bar 8/2/2023 Not Ready for Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 8/9/2023 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 8/9/2023 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 8/16/2023 Approved JOSE AVILA
Special/Order Compliance 8/16/2023 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 9/1/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 9/5/2023 Not Ready for Inspection JOSE AVILA
HVAC-Rough 9/5/2023 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 9/27/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 9/27/2023 Corrections Issued JOSE AVILA
HVAC-Rough 10/6/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 10/16/2023 Conditional Approval LILIANA PORTILLO
PLUMBING-Rough 10/16/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/27/2023 Not Ready for Inspection RONNIE MINDANAO
Green Building Rough 10/27/2023 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 10/27/2023 Not Ready for Inspection RONNIE MINDANAO
MERV13>=Rough 10/27/2023 Not Ready for Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 10/31/2023 Corrections Issued JOSE AVILA
HVAC-Rough 10/31/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 11/17/2023 No Access for Inspection SCOTT FINNILA
Green Building Rough 11/17/2023 No Access for Inspection SCOTT FINNILA
HVAC-Rough 11/17/2023 No Access for Inspection SCOTT FINNILA
MERV13>=Rough 11/17/2023 No Access for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 11/30/2023 Partial Inspection JOSE AVILA
Green Building Rough 11/30/2023 Not Ready for Inspection JOSE AVILA
HVAC-Rough 11/30/2023 Corrections Issued JOSE AVILA
MERV13>=Rough 11/30/2023 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 12/11/2023 Not Ready for Inspection CRAIG DAVIS
Green Building Rough 12/11/2023 Not Ready for Inspection CRAIG DAVIS
MERV13>=Rough 12/11/2023 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 12/14/2023 Partial Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 1/5/2024 Partial Inspection SCOTT FINNILA
Green Building Rough 1/5/2024 Partial Inspection SCOTT FINNILA
MERV13>=Rough 1/5/2024 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 1/24/2024 Corrections Issued STUART CHAPMAN
Green Building Rough 1/24/2024 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 1/24/2024 Approved STUART CHAPMAN
BUILDING-Rough-Frame 2/7/2024 Partial Approval STUART CHAPMAN
Green Building Rough 2/7/2024 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 3/11/2024 No Access for Inspection STUART CHAPMAN
Interior/Exterior Lathing 3/13/2024 Partial Approval STUART CHAPMAN
Insulation 4/3/2024 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 4/10/2024 Approved JOSEPH MCGARRY
Green Building Rough 4/10/2024 Approved JOSEPH MCGARRY
HVAC-Rough 4/10/2024 Partial Inspection JOSEPH MCGARRY
Insulation 4/10/2024 Corrections Issued JOSEPH MCGARRY
Insulation 5/3/2024 Approved RICHARD DOCKUS
Shower Pan 5/9/2024 Corrections Issued AMIR NAZARIAN
Shower Pan 5/15/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 5/21/2024 Corrections Issued RONNIE MINDANAO
Interior/Exterior Lathing 5/22/2024 Approved BRENDAN MORELLI
Drywall Nailing 8/22/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 11/27/2024 Corrections Issued JOSE MACIAS
Final 11/27/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 11/27/2024 Approved JOSE MACIAS
Green Building Final 11/27/2024 Approved JOSE MACIAS
MERV13>=Final 11/27/2024 Corrections Issued JOSE MACIAS
PLUMBING-Final 11/27/2024 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Not Required JOSE MACIAS
Smoke Detectors 11/27/2024 Approved JOSE MACIAS
Final 12/6/2024 Corrections Issued JOSE MACIAS
Final 12/12/2024 Corrections Issued ARTHUR NEGRETE
MERV13>=Final 12/12/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 12/16/2024 Corrections Issued ARTHUR NEGRETE
Final 12/16/2024 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 12/16/2024 Approved ARTHUR NEGRETE
MERV13>=Final 12/16/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 12/16/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 12/18/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 1/30/2025 Approved ARTHUR NEGRETE
Final 1/30/2025 OK to Issue CofO ARTHUR NEGRETE
HVAC-Final 1/30/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 1/30/2025 Approved ARTHUR NEGRETE