4063-4065 S EAST BLVD 90066

Certificate Information: 4063-4065 S EAST BLVD 90066

Application / Permit
22014-30000-05417
Plan Check / Job No.
B22WL04067
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental permit to # 22014-30000-01555 to add an ADU (403 sf) over garage per LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 1/4/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 REZA HAGHIGHAT
Corrections Issued 11/12/2022 REZA HAGHIGHAT
Quality Review Completed 11/15/2022 CHIHARU SUZUKI
Building Plans Picked Up 11/15/2022 APPLICANT
Plan Check Approved 12/7/2022 REZA HAGHIGHAT
Issued 1/4/2023 APPLICANT
CofO in Progress 7/21/2023 JESUS RODRIGUEZ
Permit Finaled 10/25/2023 DANIEL ORRANTE
CofO Issued 10/25/2023 DANIEL ORRANTE
Permit Finaled 10/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/2/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/2/2022 DINAH GARIN
Sewer availability Cleared 12/2/2022 DINAH GARIN
Low Impact Development Cleared 12/21/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 12/22/2022 ANTHONY MAINEZ

Contact Information

Contractor Norcio Construction Inc; Lic. No.: 1006731-B 1756 CLINTON STREET      LOS ANGELES, CA 90026
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/11/2023 Approved JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/12/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 1/12/2023 Approved JESUS RODRIGUEZ
Grounding or Bonding 1/12/2023 Partial Approval JESUS RODRIGUEZ
Sewer 1/12/2023 Not Ready for Inspection JESUS RODRIGUEZ
Underground Mechanical 1/12/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Partial Approval JESUS RODRIGUEZ
Deputy Wood Construction 2/10/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 2/13/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/13/2023 Partial Approval HERBERT GIRON
Gas Test 2/13/2023 Partial Approval HERBERT GIRON
PLUMBING-Rough 2/13/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 2/15/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 2/15/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 2/16/2023 Approved JESUS RODRIGUEZ
Gas Test 2/16/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 2/16/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 3/2/2023 Approved JESUS RODRIGUEZ
Green Building Rough 3/2/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/2/2023 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 3/2/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 3/16/2023 Approved JESUS RODRIGUEZ
Insulation 3/16/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/24/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 7/21/2023 Approved JESUS RODRIGUEZ
Final 7/21/2023 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 7/21/2023 Approved JESUS RODRIGUEZ
HVAC-Final 7/21/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 7/21/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 7/21/2023 Approved JESUS RODRIGUEZ