1142 N FRIGATE AVE 90744

Certificate Information: 1142 N FRIGATE AVE 90744

Application / Permit
22014-30000-05315
Plan Check / Job No.
B22WL04024
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st floor (109 sf) and 2nd floor (900 sf) addition to (e) single story SFD (1,282 sf) w./ att. 2-car garage (343 sf) and remodel the house
Permit Issued
Issued on 6/26/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/23/2022 REZA HAGHIGHAT
Corrections Issued 11/27/2022 REZA HAGHIGHAT
Quality Review Completed 11/30/2022 CHIHARU SUZUKI
Building Plans Picked Up 12/2/2022 APPLICANT
Applicant returned to address corrections 2/21/2023 REZA HAGHIGHAT
Applicant returned to address corrections 3/15/2023 REZA HAGHIGHAT
Plan Check Approved 5/4/2023 REZA HAGHIGHAT
Issued 6/26/2023 APPLICANT
CofO in Progress 11/5/2025 EUGENE CASSIDY
Permit Finaled 11/6/2025 ANSON MAGLASANG
CofO Issued 11/6/2025 ANSON MAGLASANG
Permit Finaled 11/6/2025 ANSON MAGLASANG

Permit Application Clearance Information

Low Impact Development Cleared 2/22/2023 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 3/13/2023 ANA SORIANO
Sewer availability Cleared 3/13/2023 ANA SORIANO
Roof/Waste drainage to street Cleared 3/16/2023 ANA SORIANO
Construction near power lines Cleared 4/24/2023 RIDWAN HARDY

Contact Information

Architect Graeber,, William Dennis; Lic. No.: C11052 418 S GREENBRIAR COURT      POST FALLS, ID 83854
Contractor Dcd+Bc Build Group Llc; Lic. No.: 1098177-B 6285 E SPRING STREET   502    LONG BEACH, CA 90808
Engineer Yaghi,, Shucri Ibrahim; Lic. No.: C43205 112 E CHAPMAN AVE STE D      ORANGE, CA 92866

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/18/2023 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 11/21/2023 Approved EUGENE CASSIDY
Footing/Foundation/Slab 11/21/2023 Approved EUGENE CASSIDY
METHANE-Barrier 11/21/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 11/21/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/29/2023 Partial Approval EUGENE CASSIDY
Green Building Rough 11/29/2023 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 11/29/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 11/29/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Partial Approval EUGENE CASSIDY
Wood Frame 1/31/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/2/2024 Corrections Issued EUGENE CASSIDY
Green Building Rough 4/2/2024 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 4/2/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 4/2/2024 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 4/2/2024 Not Ready for Inspection EUGENE CASSIDY
Deputy Wood Construction 4/3/2024 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 4/9/2024 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 4/10/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 4/10/2024 Approved EUGENE CASSIDY
Wood Frame 4/10/2024 Conditional Approval EUGENE CASSIDY
HVAC-Rough 4/30/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/30/2024 Partial Approval EUGENE CASSIDY
Shower Pan 4/30/2024 Approved EUGENE CASSIDY
Insulation 5/15/2024 Approved EUGENE CASSIDY
Drywall Nailing 5/21/2024 Partial Approval JAMES CHAVEZ
Green Building Rough 5/21/2024 Approved JAMES CHAVEZ
Drywall Nailing 5/30/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 6/26/2024 Not Ready for Inspection EUGENE CASSIDY
Shower Pan 6/26/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/9/2024 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 5/13/2025 Approved EUGENE CASSIDY
Final 5/13/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 5/13/2025 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 5/13/2025 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 5/13/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Approved EUGENE CASSIDY
Service/Power Release 5/13/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 5/13/2025 Not Ready for Inspection EUGENE CASSIDY
Final 6/24/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 6/24/2025 Approved EUGENE CASSIDY
MERV13>=Final 6/24/2025 Approved EUGENE CASSIDY
Smoke Detectors 6/24/2025 Not Ready for Inspection EUGENE CASSIDY
Final 7/31/2025 Corrections Issued EUGENE CASSIDY
Smoke Detectors 7/31/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 11/5/2025 Approved EUGENE CASSIDY
Final 11/5/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 11/5/2025 Approved EUGENE CASSIDY
PLUMBING-Final 11/5/2025 Approved EUGENE CASSIDY