3232 S SELBY AVE 90034

Certificate Information: 3232 S SELBY AVE 90034

Application / Permit
22014-30000-05290
Plan Check / Job No.
B22WL03990
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2-story addition (1,798 sf) to (e) single story SFD (896 sf), add subterranean 2-car garage (361 sf)
Permit Issued
Issued on 4/14/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/23/2022 REZA HAGHIGHAT
Corrections Issued 11/25/2022 REZA HAGHIGHAT
Quality Review Completed 11/30/2022 CHIHARU SUZUKI
Building Plans Picked Up 12/1/2022 APPLICANT
Applicant returned to address corrections 12/13/2022 REZA HAGHIGHAT
Applicant returned to address corrections 1/26/2023 REZA HAGHIGHAT
Plan Check Approved 4/6/2023 REZA HAGHIGHAT
Issued 4/14/2023 APPLICANT
CofO in Progress 5/8/2025 DAVID FEILER
Permit Finaled 5/8/2025 RICHARD STEINBACH
CofO Issued 5/8/2025 RICHARD STEINBACH
Permit Finaled 5/8/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 12/7/2022 CATHERINE ADROVER
Sewer availability Cleared 12/7/2022 CATHERINE ADROVER
Permit Cleared 12/8/2022 CATHERINE ADROVER
Miscellaneous Cleared 12/16/2022 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 12/28/2022 JENSON LEE
Hydrant and Access approval Cleared 1/13/2023 KURT CORRAL
Excavation more than 5-ft deep Cleared 2/3/2023 CALOSHA APPROVED
Trees in Parkway Cleared 2/16/2023 ADALBERTO VERA
Low Impact Development Cleared 4/3/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 4/4/2023 LIAM ODONOVAN
GPI Written Notices Cleared 4/6/2023 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 4/6/2023 REZA HAGHIGHAT

Contact Information

Architect Makim,, Vaishali Harish; Lic. No.: C29964 2470 COLBY AVENUE      LOS ANGELES, CA 90064
Contractor Owner-Builder       ,
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Geologist , ; Lic. No.: GEO2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/7/2023 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 6/9/2023 Partial Approval JESUS PINEDA
Underground Mechanical 6/9/2023 Partial Approval JESUS PINEDA
Deputy Reinf. Concrete 6/21/2023 Conditional Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 6/22/2023 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 6/22/2023 Partial Approval JOHNNY MIRANDA
Deputy Shotcrete 6/29/2023 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Partial Approval JESUS PINEDA
Insulation 8/1/2023 Not Ready for Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Partial Approval BEN MOLSTAD
Special/Order Compliance 8/23/2023 Partial Inspection CLAYTON GRAHAM
Special/Order Compliance 8/23/2023 Partial Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 10/13/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 10/25/2023 Conditional Approval JESUS PINEDA
PLUMBING-Rough 10/25/2023 Corrections Issued JESUS PINEDA
Special/Order Compliance 10/25/2023 Corrections Issued JESUS PINEDA
Gas Test 11/13/2023 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 11/13/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 11/28/2023 Approved JESUS PINEDA
PLUMBING-Rough 12/11/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Wood Construction 2/2/2024 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 2/14/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Approved JESUS PINEDA
Footing/Foundation/Slab 2/14/2024 Approved JESUS PINEDA
PLUMBING-Rough 2/14/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 2/23/2024 Approved JESUS PINEDA
Green Building Rough 2/23/2024 Approved JESUS PINEDA
Insulation 2/23/2024 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 2/23/2024 Partial Approval JESUS PINEDA
MERV13>=Rough 2/23/2024 Approved JESUS PINEDA
Reinforced Concrete Frame 2/23/2024 Approved JESUS PINEDA
Verify Sprinkler Sign Off 2/23/2024 Approved JESUS PINEDA
Insulation 2/29/2024 Approved JESUS PINEDA
Drywall Nailing 3/8/2024 Corrections Issued STEPHANIE SWANSON
Final 3/8/2024 Corrections Issued STEPHANIE SWANSON
Drywall Nailing 3/12/2024 Approved JESUS PINEDA
Shower Pan 3/19/2024 Corrections Issued OGANES TARAKHCHYAN
Shower Pan 3/21/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 4/8/2024 Approved JESUS PINEDA
Underground Mechanical 6/14/2024 Approved JESUS PINEDA
Gas Test 8/12/2024 Approved MEL KHACHATOURIAN
Underground Mechanical 8/15/2024 Approved JESUS PINEDA
PLUMBING-Final 3/13/2025 Corrections Issued WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 3/13/2025 SGSOV Not Ready WILBER ROSALES
Special/Order Compliance 3/13/2025 Partial Inspection STEPHANIE SWANSON
ELECTRICAL-Final 3/20/2025 Approved ARAM AVEDISIAN
PLUMBING-Final 3/20/2025 Approved ARAM AVEDISIAN
Service/Power Release 3/20/2025 Approved ARAM AVEDISIAN
HVAC-Final 4/15/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV Approved TEMISTOCLES CAAL
Final 4/21/2025 Corrections Issued MEL KHACHATOURIAN
Green Building Final 4/21/2025 Approved MEL KHACHATOURIAN
MERV13>=Final 4/21/2025 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 4/21/2025 SGSOV Approved MEL KHACHATOURIAN
Smoke Detectors 4/21/2025 Approved MEL KHACHATOURIAN
Deputy Drilled-In Anchors 5/8/2025 Conditional Approval DAVID FEILER
Final 5/8/2025 OK to Issue CofO DAVID FEILER