3232 S SELBY AVE 90034
Certificate Information: 3232 S SELBY AVE 90034
- Application / Permit
- 22014-30000-05290
- Plan Check / Job No.
- B22WL03990
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2-story addition (1,798 sf) to (e) single story SFD (896 sf), add subterranean 2-car garage (361 sf)
- Permit Issued
- Issued on 4/14/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | REZA HAGHIGHAT |
| Corrections Issued | 11/25/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 11/30/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/1/2022 | APPLICANT |
| Applicant returned to address corrections | 12/13/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 1/26/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 4/6/2023 | REZA HAGHIGHAT |
| Issued | 4/14/2023 | APPLICANT |
| CofO in Progress | 5/8/2025 | DAVID FEILER |
| Permit Finaled | 5/8/2025 | RICHARD STEINBACH |
| CofO Issued | 5/8/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/8/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 12/7/2022 | CATHERINE ADROVER |
| Permit | Cleared | 12/8/2022 | CATHERINE ADROVER |
| Miscellaneous | Cleared | 12/16/2022 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2022 | JENSON LEE |
| Hydrant and Access approval | Cleared | 1/13/2023 | KURT CORRAL |
| Excavation more than 5-ft deep | Cleared | 2/3/2023 | CALOSHA APPROVED |
| Trees in Parkway | Cleared | 2/16/2023 | ADALBERTO VERA |
| Low Impact Development | Cleared | 4/3/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/4/2023 | LIAM ODONOVAN |
| GPI Written Notices | Cleared | 4/6/2023 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 4/6/2023 | REZA HAGHIGHAT |
Contact Information
| Architect | Makim,, Vaishali Harish; Lic. No.: C29964 | 2470 COLBY AVENUE LOS ANGELES, CA 90064 |
| Contractor | Owner-Builder | , |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
| Geologist | , ; Lic. No.: GEO2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/7/2023 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 6/9/2023 | Partial Approval | JESUS PINEDA |
| Underground Mechanical | 6/9/2023 | Partial Approval | JESUS PINEDA |
| Deputy Reinf. Concrete | 6/21/2023 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 6/22/2023 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/22/2023 | Partial Approval | JOHNNY MIRANDA |
| Deputy Shotcrete | 6/29/2023 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2023 | Partial Approval | JESUS PINEDA |
| Insulation | 8/1/2023 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Partial Approval | BEN MOLSTAD |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | CLAYTON GRAHAM |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/13/2023 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 10/25/2023 | Conditional Approval | JESUS PINEDA |
| PLUMBING-Rough | 10/25/2023 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 10/25/2023 | Corrections Issued | JESUS PINEDA |
| Gas Test | 11/13/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Underground Mechanical | 11/13/2023 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 11/28/2023 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 12/11/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 2/2/2024 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 2/14/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 2/14/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 2/14/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/23/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 2/23/2024 | Approved | JESUS PINEDA |
| Insulation | 2/23/2024 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 2/23/2024 | Partial Approval | JESUS PINEDA |
| MERV13>=Rough | 2/23/2024 | Approved | JESUS PINEDA |
| Reinforced Concrete Frame | 2/23/2024 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 2/23/2024 | Approved | JESUS PINEDA |
| Insulation | 2/29/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 3/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 3/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 3/12/2024 | Approved | JESUS PINEDA |
| Shower Pan | 3/19/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Shower Pan | 3/21/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/8/2024 | Approved | JESUS PINEDA |
| Underground Mechanical | 6/14/2024 | Approved | JESUS PINEDA |
| Gas Test | 8/12/2024 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 8/15/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 3/13/2025 | Corrections Issued | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 3/13/2025 | SGSOV Not Ready | WILBER ROSALES |
| Special/Order Compliance | 3/13/2025 | Partial Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/20/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 3/20/2025 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 3/20/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 4/15/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Approved | TEMISTOCLES CAAL |
| Final | 4/21/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 4/21/2025 | Approved | MEL KHACHATOURIAN |
| MERV13>=Final | 4/21/2025 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 4/21/2025 | Approved | MEL KHACHATOURIAN |
| Deputy Drilled-In Anchors | 5/8/2025 | Conditional Approval | DAVID FEILER |
| Final | 5/8/2025 | OK to Issue CofO | DAVID FEILER |