6620 W 81ST ST 90045

Certificate Information: 6620 W 81ST ST 90045

Application / Permit
22014-30000-04953
Plan Check / Job No.
B22WL03794
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
1-story addition (119 sf) to (e) det. 2-car garage (360 sf)
Permit Issued
Issued on 12/14/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2022 APPLICANT
Assigned to Plan Check Engineer 10/14/2022 REZA HAGHIGHAT
Corrections Issued 10/16/2022 REZA HAGHIGHAT
Quality Review Completed 10/16/2022 KAVIAN REFAHI
Building Plans Picked Up 10/19/2022 APPLICANT
Plan Check Approved 12/5/2022 REZA HAGHIGHAT
Issued 12/14/2022 APPLICANT
CofO in Progress 6/1/2023 BOBBY KEY
Permit Finaled 6/6/2023 DANIEL ORRANTE
CofO Issued 6/6/2023 DANIEL ORRANTE
Permit Finaled 6/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/22/2022 JENSON LEE
Roof/Waste drainage to street Cleared 11/22/2022 JENSON LEE

Contact Information

Contractor Stonecastle Construction & Development Corp; Lic. No.: 601665-B 8330 LILIENTHAL AVE   UNIT B    LOS ANGELES, CA 90045
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/3/2023 Approved BOBBY KEY
Footing/Foundation/Slab 2/3/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 2/22/2023 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Approved HERBERT GIRON
Green Building Rough 2/22/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 3/9/2023 Approved BOBBY KEY
Interior/Exterior Lathing 3/23/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 3/28/2023 Approved BOBBY KEY
Green Building Rough 3/28/2023 Approved BOBBY KEY
Insulation 3/28/2023 Approved BOBBY KEY
Drywall Nailing 4/6/2023 Approved JESUS PINEDA
Final 5/24/2023 Corrections Issued BOBBY KEY
Green Building Final 5/24/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/24/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 5/24/2023 Approved BOBBY KEY
Final 6/1/2023 OK to Issue CofO BOBBY KEY