1477 S GLENDON AVE 90024
Certificate Information: 1477 S GLENDON AVE 90024
- Application / Permit
- 22014-30000-04857
- Plan Check / Job No.
- B22WL03736
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) S.F.D. and remodel throughout per engineer's calcs
- Permit Issued
- Issued on 12/30/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2022 | JASON JANGADA |
| Corrections Issued | 10/7/2022 | JASON JANGADA |
| Applicant returned to address corrections | 11/15/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 11/17/2022 | APPLICANT |
| Applicant returned to address corrections | 12/7/2022 | DAVID CASTILLO |
| Plan Check Approved | 12/30/2022 | AMY GUEVARRA |
| Issued | 12/30/2022 | APPLICANT |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
| CofO Issued | 4/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2022 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 11/3/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 11/3/2022 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 11/16/2022 | JASON JANGADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cohanfard,, Albert; Lic. No.: C45408 | 910 S BEDFORD ST 304 LOS ANGELES, CA 90035 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 4/7/2023 | Corrections Issued | CLAYTON GRAHAM |
| Excavation/Setback/Form/Re-Bar | 4/10/2023 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/10/2023 | Approved | MICHAEL PELHAM |
| METHANE-Barrier | 4/10/2023 | Approved | MICHAEL PELHAM |
| METHANE-Final | 4/10/2023 | Approved | MICHAEL PELHAM |
| METHANE-Rough | 4/10/2023 | Approved | MICHAEL PELHAM |
| METHANE-Subgrade | 4/10/2023 | Approved | MICHAEL PELHAM |
| Wood Frame | 6/27/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 8/24/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/24/2023 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 9/8/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 9/8/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 9/8/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 9/8/2023 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 9/8/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Wood Frame | 9/8/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 9/13/2023 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 9/13/2023 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 9/13/2023 | Corrections Issued | BEN MOLSTAD |
| Insulation | 9/13/2023 | Corrections Issued | BEN MOLSTAD |
| Shower Pan | 9/13/2023 | Corrections Issued | BEN MOLSTAD |
| HVAC-Rough | 9/18/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Insulation | 9/18/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/18/2023 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 9/18/2023 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 9/22/2023 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 9/22/2023 | Corrections Issued | BEN MOLSTAD |
| Wood Frame | 9/22/2023 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 9/27/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Wood Frame | 9/27/2023 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 10/4/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 10/4/2023 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 10/4/2023 | Approved | CHRISTOPHER WILSON |
| Insulation | 10/4/2023 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 10/4/2023 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 10/18/2023 | Approved | BEN MOLSTAD |
| Drywall Nailing | 10/18/2023 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 2/26/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 2/26/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 2/26/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 2/26/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 2/26/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 2/26/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 2/26/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 2/26/2024 | Approved | STEPHANIE SWANSON |
| Final | 4/1/2024 | Conditional Approval | MICHAEL PELHAM |