6448 N MARY ELLEN AVE 91401

Certificate Information: 6448 N MARY ELLEN AVE 91401

Application / Permit
22014-30000-04805
Plan Check / Job No.
B22WL03677
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New addition to construct new bedroom & bath. all work per wfpp
Permit Issued
Issued on 4/27/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2022 APPLICANT
Assigned to Plan Check Engineer 10/5/2022 AMY GUEVARRA
Corrections Issued 10/13/2022 AMY GUEVARRA
Applicant returned to address corrections 1/19/2023 JOHNPAUL ISIP
Applicant returned to address corrections 1/26/2023 JASON JANGADA
Plan Check Approved 2/3/2023 JOHNPAUL ISIP
Issued 4/27/2023 APPLICANT
CofO in Progress 3/20/2024 JOSE AVILA
Permit Finaled 8/28/2024 DANIEL ORRANTE
CofO Issued 8/28/2024 DANIEL ORRANTE
Permit Finaled 8/28/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/12/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 2/1/2023 COLIN LOREDO
Sewer availability Cleared 2/1/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/5/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/11/2023 Approved KIRK SANDERS
Deputy Drilled-In Anchors 7/21/2023 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 7/26/2023 Partial Approval KIRK SANDERS
Green Building Rough 7/26/2023 Not Ready for Inspection KIRK SANDERS
Wood Frame 7/26/2023 Partial Approval KIRK SANDERS
Underground Mechanical 8/2/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Corrections Issued CHRISTOPHER ROJAS
Insulation 9/6/2023 Partial Approval CHRISTOPHER ROJAS
Insulation 9/6/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Partial Approval KIRK SANDERS
Rough-Elec/Plmb/HVAC 9/25/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 10/17/2023 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 10/17/2023 Approved KIRK SANDERS
HVAC-Rough 10/17/2023 Approved KIRK SANDERS
PLUMBING-Rough 10/17/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 10/30/2023 Approved CHRISTOPHER ROJAS
Insulation 11/3/2023 Approved JUAN VALENZUELA
Drywall Nailing 12/11/2023 Corrections Issued JOSE AVILA
Green Building Rough 12/11/2023 Approved JOSE AVILA
Shower Pan 12/11/2023 Approved JOSE AVILA
Drywall Nailing 12/19/2023 Approved JOSE AVILA
Interior/Exterior Lathing 12/21/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/15/2024 Approved JOSE AVILA
ELECTRICAL-Final 3/15/2024 Partial Approval JOSE AVILA
HVAC-Final 3/15/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 3/15/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/15/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 3/15/2024 Approved JOSE AVILA
Final 3/19/2024 OK to Issue CofO JOSE AVILA
Green Building Final 3/19/2024 Approved JOSE AVILA