1371 W 27TH ST 90731
Certificate Information: 1371 W 27TH ST 90731
- Application / Permit
- 22014-30000-04790
- Plan Check / Job No.
- B22WL03654
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2-story addition (1,716 sf) to (e) single story SFD (800 sf) per DIR-2023-1865-CDP
- Permit Issued
- Issued on 1/4/2024
- Issuing Office
- San Pedro
- Current Status
- Issued on 1/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2022 | REZA HAGHIGHAT |
| Corrections Issued | 11/13/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 11/26/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 11/28/2022 | APPLICANT |
| Applicant returned to address corrections | 10/23/2023 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 11/22/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 12/29/2023 | REZA HAGHIGHAT |
| Issued | 1/4/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2022 | ANA SORIANO |
| Sewer availability | Cleared | 11/23/2022 | ANA SORIANO |
| Low Impact Development | Cleared | 9/1/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 9/5/2023 | ANA SORIANO |
| GPI Written Notices | Cleared | 10/23/2023 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 10/23/2023 | REZA HAGHIGHAT |
| Coastal Zone | Cleared | 11/13/2023 | JOE TAM |
| Miscellaneous | Cleared | 11/13/2023 | JOE TAM |
| Specific Plan | Cleared | 11/13/2023 | JOE TAM |
| ZA Case | Cleared | 11/13/2023 | JOE TAM |
| Hydrant and Access approval | Cleared | 12/7/2023 | RUEL COLE |
Contact Information
| Contractor | Rodcrete C Development; Lic. No.: 842017-B | 8482 HOLDER ST BUENA PARK, CA 90620 |
| Engineer | Tiongco,, John Lazarraga; Lic. No.: C70915 | 17715 CANEHILL AVE BELLFLOWER, CA 90706 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/13/2024 | Conditional Approval | ANSON MAGLASANG |
| Pre-Inspection | 2/16/2024 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 2/29/2024 | Conditional Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 3/8/2024 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2024 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Partial Approval | JAMES CHAVEZ |
| HVAC-Rough | 5/17/2024 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 5/17/2024 | Approved | ANSON MAGLASANG |
| Special/Order Compliance | 6/4/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/14/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 6/14/2024 | Partial Approval | JAMES CHAVEZ |
| Underground Mechanical | 6/14/2024 | Partial Approval | JAMES CHAVEZ |
| Insulation | 7/15/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Shower Pan | 7/15/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Insulation | 7/18/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 7/18/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Drywall Nailing | 8/6/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 8/6/2024 | Approved | JOSEPH MCGARRY |
| Shower Pan | 8/6/2024 | Approved | JOSEPH MCGARRY |
| Wood Frame | 8/6/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/28/2024 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 10/18/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 12/6/2024 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/24/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 12/24/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/20/2025 | Approved | JOSEPH MCGARRY |
| Final | 8/20/2025 | No Access for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/20/2025 | Approved | JOSEPH MCGARRY |
| Green Building Final | 8/20/2025 | No Access for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 8/20/2025 | No Access for Inspection | JOSEPH MCGARRY |
| Final | 10/2/2025 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 10/2/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 10/2/2025 | Approved | JOSEPH MCGARRY |
| Final | 11/21/2025 | Corrections Issued | JOSEPH MCGARRY |