5843 W 78TH ST 90045
Certificate Information: 5843 W 78TH ST 90045
- Application / Permit
- 22014-30000-04721
- Plan Check / Job No.
- B22WL03595
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MASTER BEDROOM/BATH ADDTION TO AN (E) SFD.
- Permit Issued
- Issued on 1/27/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2022 | ALFREDO JARA |
| Corrections Issued | 9/28/2022 | ALFREDO JARA |
| Building Plans Picked Up | 9/29/2022 | APPLICANT |
| Applicant returned to address corrections | 11/18/2022 | ALFREDO JARA |
| Plan Check Approved | 11/28/2022 | RICHARD GARCIA |
| Issued | 1/27/2023 | APPLICANT |
| CofO in Progress | 10/18/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 10/24/2023 | DANIEL ORRANTE |
| CofO Issued | 10/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 11/1/2022 | SAUL GARCIA |
| Low Impact Development | Cleared | 11/9/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 11/9/2022 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 11/18/2022 | ALFREDO JARA |
Contact Information
| Contractor | Reliance Builders Llc; Lic. No.: 1000372-B | 11500 W OLYMPIC BLVD STE 536 LOS ANGELES, CA 90064 |
| Engineer | Attaalla,, Sayed Ahmed; Lic. No.: S5339 | 11254 HANNUM AVE CULVER CITY, CA 90230 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/22/2023 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 3/8/2023 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 3/8/2023 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 3/9/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Conditional Approval | BOBBY KEY |
| Deputy Wood Construction | 4/6/2023 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 4/24/2023 | Corrections Issued | BOBBY KEY |
| Final | 4/24/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 4/24/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 5/15/2023 | Approved | BOBBY KEY |
| Green Building Rough | 5/15/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 5/15/2023 | Partial Approval | BOBBY KEY |
| Insulation | 5/22/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 5/30/2023 | Approved | RICHARD STEINBACH |
| Final | 6/9/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 6/9/2023 | Approved | BOBBY KEY |
| Shower Pan | 6/9/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/5/2023 | Approved | JESUS RODRIGUEZ |
| Final | 10/5/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 10/5/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 10/5/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/5/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/5/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 10/5/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 10/12/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Smoke Detectors | 10/12/2023 | Approved | JESUS RODRIGUEZ |
| Final | 10/18/2023 | OK to Issue CofO | JESUS RODRIGUEZ |