4250 S INGLEWOOD BLVD 90066
Certificate Information: 4250 S INGLEWOOD BLVD 90066
- Application / Permit
- 22014-30000-04678
- Plan Check / Job No.
- B22WL03573
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Garage Conversion and Addition to ADU per LAMC 12.22 A.33(c)( and (d)
- Permit Issued
- Issued on 11/15/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2022 | DAVID CASTILLO |
| Corrections Issued | 9/27/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 10/3/2022 | APPLICANT |
| Applicant returned to address corrections | 11/10/2022 | DAVID CASTILLO |
| Plan Check Approved | 11/15/2022 | EDWIN ESPIN |
| Issued | 11/15/2022 | APPLICANT |
| CofO in Progress | 1/24/2024 | RICHARD STEINBACH |
| Permit Finaled | 1/30/2024 | DANIEL ORRANTE |
| CofO Issued | 1/30/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/30/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/4/2022 | AHMED AMARRAGY |
| Roof/Waste drainage to street | Cleared | 10/4/2022 | AHMED AMARRAGY |
| Sewer availability | Cleared | 10/4/2022 | AHMED AMARRAGY |
| Tenant Habitability Plan | Cleared | 10/4/2022 | MICHAEL SOTO |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2022 | AHMED AMARRAGY |
| Specific Plan | Cleared | 11/7/2022 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shokoufandeh,, Bahman; Lic. No.: C49709 | 13024 SKY VALLEY ROAD LOS ANGELES, CA 90049 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/24/2023 | Partial Inspection | HERBERT GIRON |
| PLUMBING-Rough | 3/30/2023 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/6/2023 | Corrections Issued | HERBERT GIRON |
| Sewer | 5/1/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 5/1/2023 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 5/4/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/4/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/13/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/14/2023 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/13/2023 | Approved | BOBBY KEY |
| Green Building Rough | 9/13/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 9/13/2023 | Partial Approval | BOBBY KEY |
| Insulation | 9/13/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 9/13/2023 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 10/13/2023 | Approved | TEMISTOCLES CAAL |
| Insulation | 10/13/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 10/25/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 11/3/2023 | Corrections Issued | TEMISTOCLES CAAL |
| Shower Pan | 11/8/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/15/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/9/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 1/9/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 1/9/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 1/9/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 1/9/2024 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 1/9/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/19/2024 | Approved | JESUS RODRIGUEZ |
| Final | 1/19/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| HVAC-Final | 1/19/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 1/19/2024 | Approved | JESUS RODRIGUEZ |