916-916 1/2 E VERNON AVE 90291
Certificate Information: 916-916 1/2 E VERNON AVE 90291
- Application / Permit
- 22014-30000-04582
- Plan Check / Job No.
- B22WL03497
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 STORY HOUSE ADDITION AND MAJOR REMODEL W/ ATTACHED GARAGE AND NEW ATTACHED ADU PER STATE LAW.
- Permit Issued
- Issued on 10/20/2022
- Issuing Office
- Current Status
- CofO Issued on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | KAVIAN REFAHI |
| Corrections Issued | 9/25/2022 | KAVIAN REFAHI |
| Quality Review Completed | 9/28/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 10/3/2022 | KAVIAN REFAHI |
| Plan Check Approved | 10/17/2022 | KAVIAN REFAHI |
| Issued | 10/20/2022 | APPLICANT |
| Building Plans Picked Up | 10/24/2022 | APPLICANT |
| CofO in Progress | 11/21/2024 | HERBERT GIRON |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
| CofO Issued | 12/3/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2022 | JOSE HERNANDEZ |
| Permit | Cleared | 9/24/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 9/26/2022 | JOSE HERNANDEZ |
| Low Impact Development | Cleared | 9/30/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/1/2022 | JOSE HERNANDEZ |
| Specific Plan | Cleared | 10/3/2022 | FREDDY GARCIA |
| Trees in Parkway | Cleared | 10/5/2022 | ADALBERTO VERA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/13/2023 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 1/18/2023 | Conditional Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 2/15/2023 | Conditional Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 2/17/2023 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 2/17/2023 | Approved | EVAN COOPER |
| Deputy Wood Construction | 3/9/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/5/2023 | No Access for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | No Access for Inspection | EVAN COOPER |
| Green Building Rough | 5/5/2023 | No Access for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | EVAN COOPER |
| Wood Frame | 5/8/2023 | Not Ready for Inspection | EVAN COOPER |
| Deputy Wood Construction | 5/9/2023 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Rough | 6/20/2023 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 6/20/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 6/20/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 7/17/2023 | Corrections Issued | EVAN COOPER |
| Shower Pan | 7/17/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 7/25/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 8/14/2023 | Approved | HERBERT GIRON |
| Final | 8/14/2023 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Final | 8/14/2023 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 8/14/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 8/14/2023 | Conditional Approval | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/14/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 8/14/2023 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 8/14/2023 | Approved | HERBERT GIRON |
| Insulation | 9/1/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 9/12/2023 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/18/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 7/24/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 8/30/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Gas Test | 8/30/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 8/30/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 8/30/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 9/25/2024 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 9/25/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 10/2/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 10/2/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 10/29/2024 | Approved | HERBERT GIRON |
| Final | 10/29/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 10/29/2024 | Approved | HERBERT GIRON |
| Final | 11/20/2024 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 11/20/2024 | Approved | HERBERT GIRON |