7950 S CHASE AVE 90045

Certificate Information: 7950 S CHASE AVE 90045

Application / Permit
22014-30000-04458
Plan Check / Job No.
B22WL03403
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) Detached Garage Addition for ADU per LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 12/7/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2022 APPLICANT
Assigned to Plan Check Engineer 9/13/2022 ALFREDO JARA
Corrections Issued 9/14/2022 ALFREDO JARA
Applicant returned to address corrections 11/18/2022 DAVID CASTILLO
Building Plans Picked Up 11/22/2022 APPLICANT
Plan Check Approved 12/2/2022 RICHARD GARCIA
Issued 12/7/2022 APPLICANT
CofO in Progress 9/11/2024 BOBBY KEY
Permit Finaled 9/16/2024 RICHARD STEINBACH
CofO Issued 9/16/2024 RICHARD STEINBACH
Permit Finaled 9/16/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/27/2022 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 10/12/2022 CATHERINE ADROVER
Sewer availability Cleared 10/12/2022 CATHERINE ADROVER
Low Impact Development Cleared 10/24/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 10/26/2022 CATHERINE ADROVER
Construction near power lines Cleared 11/9/2022 RIDWAN HARDY
Construction within easement Cleared 11/9/2022 RIDWAN HARDY
GPI Written Notices Cleared 11/18/2022 ALFREDO JARA
Grading Pre-Inspection Cleared 11/18/2022 ALFREDO JARA

Contact Information

Architect Pisani,, Tanya Chan; Lic. No.: C31357 11935 BEATRICE STREET      LOS ANGELES, CA 90230
Contractor Fischer Joel Construction Inc; Lic. No.: 528992-B PO BOX 341338      LOS ANGELES, CA 90064
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/27/2023 Approved BOBBY KEY
Footing/Foundation/Slab 1/27/2023 Approved BOBBY KEY
METHANE-Barrier 1/27/2023 Approved BOBBY KEY
METHANE-Subgrade 1/27/2023 Approved BOBBY KEY
Deputy Drilled-In Anchors 5/2/2023 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Partial Approval BOBBY KEY
HVAC-Rough 6/9/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 6/9/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Partial Approval BOBBY KEY
HVAC-Rough 8/28/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 9/11/2023 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 9/11/2023 Not Ready for Inspection TEMISTOCLES CAAL
Deputy Wood Construction 9/27/2023 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 10/2/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Approved BOBBY KEY
HVAC-Rough 10/2/2023 Approved BOBBY KEY
PLUMBING-Rough 10/2/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 11/1/2023 Not Ready for Inspection BOBBY KEY
Green Building Rough 11/1/2023 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 11/1/2023 Not Ready for Inspection BOBBY KEY
Verify Sprinkler Sign Off 11/1/2023 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 11/17/2023 Approved JESUS RODRIGUEZ
Green Building Rough 11/17/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/17/2023 Approved JESUS RODRIGUEZ
Special/Order Compliance 11/17/2023 Corrections Issued JESUS RODRIGUEZ
Verify Sprinkler Sign Off 11/17/2023 Approved JESUS RODRIGUEZ
Insulation 12/4/2023 Approved BOBBY KEY
Drywall Nailing 12/8/2023 Approved BOBBY KEY
Gas Test 2/16/2024 Approved BOBBY KEY
PLUMBING-Rough 2/16/2024 Approved BOBBY KEY
Sewer 2/16/2024 Approved BOBBY KEY
Interior/Exterior Lathing 5/17/2024 Approved BOBBY KEY
HVAC-Rough 6/4/2024 Approved BOBBY KEY
Underground Mechanical 6/4/2024 Partial Approval BOBBY KEY
ELECTRICAL-Final 6/21/2024 Approved BOBBY KEY
PLUMBING-Final 6/21/2024 Approved BOBBY KEY
HVAC-Final 6/26/2024 Corrections Issued BOBBY KEY
Final 9/11/2024 OK to Issue CofO BOBBY KEY
Green Building Final 9/11/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/11/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 9/11/2024 Approved BOBBY KEY