3880 S GRAMERCY PL 90062
Certificate Information: 3880 S GRAMERCY PL 90062
- Application / Permit
- 22014-30000-04407
- Plan Check / Job No.
- B22WL03370
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new detached 2-story unit with roof deck per SB9 Two-Unit Development Ca Govt Code 65852.21 (convert existing garage to habitable area as port of new unit)
- Permit Issued
- Issued on 10/30/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | KAVIAN REFAHI |
| Corrections Issued | 9/11/2022 | KAVIAN REFAHI |
| Quality Review Completed | 9/16/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 9/19/2022 | APPLICANT |
| Applicant returned to address corrections | 11/8/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 11/21/2022 | KAVIAN REFAHI |
| Plan Check Approved | 12/9/2022 | KAVIAN REFAHI |
| Issued | 10/30/2024 | APPLICANT |
| CofO in Progress | 10/14/2025 | SABAS ALONSO |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
| CofO Issued | 10/17/2025 | DEROLD HAUFF |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2022 | JEANIE LAM |
| Permit | Cleared | 9/23/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2022 | JEANIE LAM |
| Sewer availability | Cleared | 9/30/2022 | JEANIE LAM |
| Senate Bill 9 | Cleared | 10/11/2022 | CLAUDE GOODING |
| Trees in Parkway | Cleared | 10/12/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 10/21/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/24/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 10/25/2022 | TINA MIRANDA |
| Hydrant and Access approval | Cleared | 10/31/2022 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/8/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 11/8/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 11/15/2024 | No Access for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 11/16/2024 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 11/20/2024 | Corrections Issued | SABAS ALONSO |
| Deputy Steel/Welding | 12/13/2024 | Conditional Approval | SABAS ALONSO |
| Pre-Inspection | 12/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 1/10/2025 | Approved | SABAS ALONSO |
| Sewer | 1/22/2025 | Approved | SABAS ALONSO |
| Deputy Steel/Welding | 1/27/2025 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Corrections Issued | MICHAEL LEWIS |
| Deputy Wood Construction | 2/27/2025 | Conditional Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 4/2/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 4/7/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/7/2025 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 4/7/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/17/2025 | Approved | SABAS ALONSO |
| Shower Pan | 4/17/2025 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 4/17/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/1/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 5/1/2025 | Approved | SABAS ALONSO |
| Insulation | 5/8/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 5/13/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/5/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 7/17/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 7/24/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 7/24/2025 | Approved | SABAS ALONSO |
| Final | 8/8/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 8/8/2025 | Approved | SABAS ALONSO |
| Gas Test | 8/8/2025 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 8/8/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 8/8/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 8/8/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 8/8/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 8/8/2025 | Approved | SABAS ALONSO |
| Final | 9/30/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 9/30/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | SABAS ALONSO |
| Final | 10/9/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 10/9/2025 | Approved | SABAS ALONSO |