7548 S RINDGE AVE 90293

Certificate Information: 7548 S RINDGE AVE 90293

Application / Permit
22014-30000-04372
Plan Check / Job No.
B22WL03306
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition (1,045 sf) and remodel to (e) 2-story SFD (2,572 sf) with att. subterranean garage (445 sf), add to garage (62 sf)
Permit Issued
Issued on 1/26/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 REZA HAGHIGHAT
Corrections Issued 9/13/2022 REZA HAGHIGHAT
Quality Review Completed 9/19/2022 CHIHARU SUZUKI
Applicant returned to address corrections 11/14/2022 REZA HAGHIGHAT
Plan Check Approved 1/3/2023 REZA HAGHIGHAT
Issued 1/26/2023 APPLICANT
CofO in Progress 12/24/2024 JESUS PINEDA
Permit Finaled 12/31/2024 RICHARD STEINBACH
CofO Issued 12/31/2024 RICHARD STEINBACH
Permit Finaled 12/31/2024 RICHARD STEINBACH

Permit Application Clearance Information

Coastal Zone Cleared 12/12/2022 JASON CHAN
Low Impact Development Cleared 12/20/2022 DEBORA LEITE
Eng Process Fee Ord 176,300 Cleared 12/27/2022 JENSON LEE
Sewer availability Cleared 12/27/2022 JENSON LEE
Roof/Waste drainage to street Cleared 12/28/2022 JENSON LEE
Excavation more than 5-ft deep Cleared 1/3/2023 CALOSHA APPROVED
GPI Written Notices Cleared 1/3/2023 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 1/3/2023 REZA HAGHIGHAT

Contact Information

Contractor Pearl Remodeling; Lic. No.: 955824-B 6803 YARMOUTH AVENUE      RESEDA, CA 91335
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/24/2023 Approved BOBBY KEY
Footing/Foundation/Slab 5/24/2023 Partial Approval BOBBY KEY
Underground Mechanical 6/8/2023 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 6/28/2023 Approved BOBBY KEY
Wood Frame 7/26/2023 Partial Approval BOBBY KEY
Deputy Drilled-In Anchors 8/28/2023 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 8/28/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Conditional Approval BOBBY KEY
Deputy Wood Construction 2/7/2024 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/26/2024 Corrections Issued JESUS RODRIGUEZ
Special/Order Compliance 2/26/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 3/28/2024 Approved BOBBY KEY
ELECTRICAL-Rough 4/10/2024 Approved BOBBY KEY
Interior/Exterior Lathing 4/10/2024 Partial Approval BOBBY KEY
HVAC-Rough 4/12/2024 Approved BOBBY KEY
Special/Order Compliance 4/12/2024 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 4/15/2024 Partial Approval BOBBY KEY
Green Building Rough 4/15/2024 Approved BOBBY KEY
Insulation 4/15/2024 Approved BOBBY KEY
Deputy Wood Construction 4/19/2024 Conditional Approval RICHARD STEINBACH
BUILDING-Rough-Frame 4/24/2024 Approved RICHARD STEINBACH
Shower Pan 4/24/2024 Approved RICHARD STEINBACH
Drywall Nailing 5/3/2024 Partial Approval BOBBY KEY
Interior/Exterior Lathing 5/14/2024 Approved BOBBY KEY
Special/Order Compliance 7/19/2024 Corrections Issued BOBBY KEY
Gas Test 8/5/2024 Approved BOBBY KEY
PLUMBING-Final 10/8/2024 Approved BOBBY KEY
HVAC-Final 10/24/2024 Approved BOBBY KEY
ELECTRICAL-Final 10/25/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Final 10/31/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 12/23/2024 Approved JESUS PINEDA
Final 12/23/2024 OK to Issue CofO JESUS PINEDA
Green Building Final 12/23/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Approved JESUS PINEDA
Smoke Detectors 12/23/2024 Approved JESUS PINEDA