1700 W MIRACOSTA ST 90732

Certificate Information: 1700 W MIRACOSTA ST 90732

Application / Permit
22014-30000-04258
Plan Check / Job No.
B22WL03230
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel, Enlargment of Kitchen and Dining Room by Addition to the Rear of an (E) 1-Story S.F.D
Permit Issued
Issued on 1/4/2023
Issuing Office
Current Status
CofO Issued on 6/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2022 APPLICANT
Assigned to Plan Check Engineer 9/6/2022 EDWIN ESPIN
Corrections Issued 9/6/2022 EDWIN ESPIN
Applicant returned to address corrections 9/26/2022 DAVID CASTILLO
Applicant returned to address corrections 10/17/2022 EDWIN ESPIN
Applicant returned to address corrections 10/20/2022 EDWIN ESPIN
Plan Check Approved 11/8/2022 DAVID CASTILLO
Building Plans Picked Up 11/9/2022 APPLICANT
Issued 1/4/2023 APPLICANT
CofO in Progress 6/12/2025 MICHAEL PELHAM
CofO Issued 6/12/2025 RICHARD STEINBACH
Permit Finaled 6/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/15/2022 HUGO LOPEZ
Sewer availability Cleared 9/15/2022 HUGO LOPEZ
Grading Pre-Inspection Cleared 9/26/2022 EDWIN ESPIN
Roof/Waste drainage to street Cleared 10/26/2022 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/13/2023 Not Ready for Inspection EUGENE CASSIDY
Deputy Wood Construction 2/23/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 3/17/2023 Approved JOHN KLARIN
HVAC-Rough 3/17/2023 Approved JOHN KLARIN
Insulation 3/17/2023 Approved JOHN KLARIN
PLUMBING-Rough 3/17/2023 Approved JOHN KLARIN
Wood Frame 3/17/2023 Corrections Issued JOHN KLARIN
Deputy Wood Construction 3/20/2023 Conditional Approval ANSON MAGLASANG
ELECTRICAL-Rough 3/21/2023 No Access for Inspection JAMES CHAVEZ
HVAC-Rough 3/21/2023 No Access for Inspection JAMES CHAVEZ
Insulation 3/21/2023 No Access for Inspection JAMES CHAVEZ
PLUMBING-Rough 3/21/2023 No Access for Inspection JAMES CHAVEZ
Wood Frame 3/21/2023 No Access for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 3/23/2023 Approved JOHN KLARIN
HVAC-Rough 3/23/2023 Approved JOHN KLARIN
Insulation 3/23/2023 Partial Approval JOHN KLARIN
PLUMBING-Rough 3/23/2023 Approved JOHN KLARIN
Wood Frame 3/23/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 4/7/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 4/11/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 4/18/2023 Not Ready for Inspection ANSON MAGLASANG
Interior/Exterior Lathing 5/8/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/1/2023 Approved JOHN KLARIN
Drywall Nailing 6/1/2023 Approved JOHN KLARIN
Final 6/1/2023 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 6/1/2023 Approved JOHN KLARIN
Green Building Final 6/1/2023 Approved JOHN KLARIN
Green Building Rough 6/1/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 6/1/2023 Approved JOHN KLARIN
Final 6/6/2023 Corrections Issued JOHN KLARIN
Final 5/9/2025 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 5/20/2025 Approved BEN MOLSTAD
Final 5/20/2025 Corrections Issued BEN MOLSTAD
HVAC-Final 5/20/2025 Approved BEN MOLSTAD
PLUMBING-Final 5/20/2025 Approved BEN MOLSTAD
Rough-Elec/Plmb/HVAC 5/20/2025 Approved BEN MOLSTAD
Final 6/12/2025 OK to Issue CofO MICHAEL PELHAM