617 E 85TH ST 90001
Certificate Information: 617 E 85TH ST 90001
- Application / Permit
- 22014-30000-04158
- Plan Check / Job No.
- B22WL03163
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel and enlarge attached garage in the front of a SFD.
- Permit Issued
- Issued on 4/6/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2022 | JAHANSHAH POURHASSAN |
| Corrections Issued | 8/29/2022 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 8/30/2022 | APPLICANT |
| Applicant returned to address corrections | 9/28/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 1/19/2023 | JOHNPAUL ISIP |
| Issued | 4/6/2023 | APPLICANT |
| CofO in Progress | 10/31/2024 | MICHAEL LEWIS |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
| CofO Issued | 11/1/2024 | DEROLD HAUFF |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 11/2/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2022 | WALLIE JONG |
| Sewer availability | Cleared | 11/3/2022 | WALLIE JONG |
| Trees in Parkway | Cleared | 11/8/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 12/1/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 12/7/2022 | WALLIE JONG |
| Construction within easement | Cleared | 1/8/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Rehab Building Co Inc; Lic. No.: 991087-B | 17130 VAN BUREN 556 RIVERSIDE, CA 92504 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/21/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 9/25/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 9/25/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 11/29/2023 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 11/29/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/17/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 1/17/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/17/2024 | Approved | MICHAEL LEWIS |
| Final | 3/1/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 3/1/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 3/1/2024 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 3/1/2024 | Approved | MICHAEL LEWIS |
| Final | 5/14/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 10/28/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 10/30/2024 | OK to Issue CofO | MICHAEL LEWIS |