2854 S FORRESTER DR 90064

Certificate Information: 2854 S FORRESTER DR 90064

Application / Permit
22014-30000-04059
Plan Check / Job No.
B22WL03092
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story House addition w/ new basement and attached ADU , entire S.F.D. being removed except 2' of foundation
Permit Issued
Issued on 5/25/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 TARIK SAOUD
Corrections Issued 8/21/2022 TARIK SAOUD
Quality Review Completed 9/6/2022 CHIHARU SUZUKI
Applicant returned to address corrections 10/17/2022 YASHAR EMAMI
Applicant returned to address corrections 10/20/2022 YASHAR EMAMI
Plan Check Approved 11/10/2022 YASHAR EMAMI
Building Plans Picked Up 11/10/2022 APPLICANT
Issued 5/25/2023 APPLICANT
CofO in Progress 4/24/2025 MICHAEL PELHAM
Permit Finaled 4/24/2025 RICHARD STEINBACH
CofO Issued 4/24/2025 RICHARD STEINBACH
Permit Finaled 4/24/2025 RICHARD STEINBACH

Permit Application Clearance Information

Trees in Parkway Cleared 8/25/2022 ADALBERTO VERA
Sewer availability Cleared 8/26/2022 JENSON LEE
Specific Plan Cleared 8/29/2022 FREDDY GARCIA
Address approval Cleared 8/30/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 8/30/2022 JENSON LEE
Permit Cleared 8/30/2022 JENSON LEE
Low Impact Development Cleared 9/19/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/20/2022 JENSON LEE
Excavation more than 5-ft deep Cleared 11/10/2022 CALOSHA APPROVED
Grading Pre-Inspection Cleared 11/10/2022 TARIK SAOUD

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor C R J Construction; Lic. No.: 1025947-B 23679 CALABASAS RD #973      CALABASAS, CA 91302
Engineer Le,, Thang Huu; Lic. No.: C63174 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/17/2023 Corrections Issued CLAYTON GRAHAM
Footing/Foundation/Slab 8/17/2023 Off-Hour Fees Due
Footing/Foundation/Slab 9/18/2023 Partial Inspection CARLOS MATAMOROS
METHANE-Barrier 9/18/2023 Approved CARLOS MATAMOROS
METHANE-Subgrade 9/18/2023 Corrections Issued CARLOS MATAMOROS
METHANE-Subgrade 11/7/2023 Corrections Issued OGANES TARAKHCHYAN
METHANE-Rough 11/8/2023 Corrections Issued OGANES TARAKHCHYAN
METHANE-Subgrade 11/13/2023 Approved OGANES TARAKHCHYAN
Special/Order Compliance 11/20/2023 Corrections Issued KENNETH NAGLE
Underground Mechanical 11/20/2023 No Access for Inspection KENNETH NAGLE
Underground Mechanical 11/28/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/18/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/19/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/4/2024 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 6/17/2024 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 6/21/2024 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 6/21/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 6/25/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 7/3/2024 Corrections Issued SEAN HAUPT
Gas Test 7/3/2024 Partial Approval SEAN HAUPT
PLUMBING-Rough 7/3/2024 Approved SEAN HAUPT
ELECTRICAL-Final 7/9/2024 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 7/9/2024 Conditional Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 7/11/2024 Corrections Issued ASHLEY THOMPSON
Green Building Rough 7/11/2024 Approved ASHLEY THOMPSON
METHANE-Rough 7/11/2024 Not Ready for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 7/17/2024 Approved SEAN HAUPT
METHANE-Rough 7/17/2024 Approved SEAN HAUPT
Insulation 7/24/2024 Partial Approval TEMISTOCLES CAAL
Shower Pan 7/24/2024 Approved TEMISTOCLES CAAL
Insulation 7/30/2024 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 7/30/2024 Approved STEPHANIE SWANSON
Final 8/1/2024 Corrections Issued ASHLEY THOMPSON
Insulation 8/1/2024 Approved ASHLEY THOMPSON
Drywall Nailing 8/12/2024 Approved REGINA MENDEZ
Drywall Nailing 8/12/2024 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Final 8/12/2024 Corrections Issued REGINA MENDEZ
Smoke Detectors 8/12/2024 Corrections Issued REGINA MENDEZ
Sewer 12/2/2024 Approved REGINA MENDEZ
ELECTRICAL-Final 2/20/2025 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 3/5/2025 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 3/7/2025 Corrections Issued BOBBY KEY
Gas Test 3/7/2025 Corrections Issued BOBBY KEY
HVAC-Final 3/7/2025 Approved BOBBY KEY
PLUMBING-Final 3/7/2025 Corrections Issued BOBBY KEY
Smoke Detectors 3/7/2025 Approved BOBBY KEY
Special/Order Compliance 3/7/2025 Partial Inspection WILBER ROSALES
ELECTRICAL-Final 3/12/2025 Not Ready for Inspection ASHLEY THOMPSON
Gas Test 3/12/2025 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 3/12/2025 Partial Approval ASHLEY THOMPSON
Gas Test 3/13/2025 Approved ARAM AVEDISIAN
PLUMBING-Final 3/13/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Approved EVAN COOPER
Service/Power Release 4/7/2025 Approved EVAN COOPER
ELECTRICAL-Final 4/9/2025 Not Ready for Inspection ASHLEY THOMPSON
Final 4/9/2025 Corrections Issued ASHLEY THOMPSON
Green Building Final 4/9/2025 Approved ASHLEY THOMPSON
Deputy Drilled-In Anchors 4/11/2025 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 4/11/2025 Conditional Approval MICHAEL PELHAM
Special/Order Compliance 4/14/2025 Corrections Issued MICHAEL PELHAM
Final 4/16/2025 Partial Approval KIRK SANDERS
Final 4/24/2025 OK to Issue CofO MICHAEL PELHAM
Service/Power Release 4/24/2025 Approved MICHAEL PELHAM