2854 S FORRESTER DR 90064
Certificate Information: 2854 S FORRESTER DR 90064
- Application / Permit
- 22014-30000-04059
- Plan Check / Job No.
- B22WL03092
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story House addition w/ new basement and attached ADU , entire S.F.D. being removed except 2' of foundation
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | TARIK SAOUD |
| Corrections Issued | 8/21/2022 | TARIK SAOUD |
| Quality Review Completed | 9/6/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 10/17/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 10/20/2022 | YASHAR EMAMI |
| Plan Check Approved | 11/10/2022 | YASHAR EMAMI |
| Building Plans Picked Up | 11/10/2022 | APPLICANT |
| Issued | 5/25/2023 | APPLICANT |
| CofO in Progress | 4/24/2025 | MICHAEL PELHAM |
| Permit Finaled | 4/24/2025 | RICHARD STEINBACH |
| CofO Issued | 4/24/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/24/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 8/25/2022 | ADALBERTO VERA |
| Sewer availability | Cleared | 8/26/2022 | JENSON LEE |
| Specific Plan | Cleared | 8/29/2022 | FREDDY GARCIA |
| Address approval | Cleared | 8/30/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2022 | JENSON LEE |
| Permit | Cleared | 8/30/2022 | JENSON LEE |
| Low Impact Development | Cleared | 9/19/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | JENSON LEE |
| Excavation more than 5-ft deep | Cleared | 11/10/2022 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 11/10/2022 | TARIK SAOUD |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | C R J Construction; Lic. No.: 1025947-B | 23679 CALABASAS RD #973 CALABASAS, CA 91302 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 8/17/2023 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 9/18/2023 | Partial Inspection | CARLOS MATAMOROS |
| METHANE-Barrier | 9/18/2023 | Approved | CARLOS MATAMOROS |
| METHANE-Subgrade | 9/18/2023 | Corrections Issued | CARLOS MATAMOROS |
| METHANE-Subgrade | 11/7/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| METHANE-Rough | 11/8/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 11/13/2023 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 11/20/2023 | Corrections Issued | KENNETH NAGLE |
| Underground Mechanical | 11/20/2023 | No Access for Inspection | KENNETH NAGLE |
| Underground Mechanical | 11/28/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/18/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/4/2024 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 6/17/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/21/2024 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 6/21/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 6/25/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/3/2024 | Corrections Issued | SEAN HAUPT |
| Gas Test | 7/3/2024 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 7/3/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 7/9/2024 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 7/9/2024 | Conditional Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 7/11/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 7/11/2024 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 7/11/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 7/17/2024 | Approved | SEAN HAUPT |
| METHANE-Rough | 7/17/2024 | Approved | SEAN HAUPT |
| Insulation | 7/24/2024 | Partial Approval | TEMISTOCLES CAAL |
| Shower Pan | 7/24/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 7/30/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/30/2024 | Approved | STEPHANIE SWANSON |
| Final | 8/1/2024 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 8/1/2024 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 8/12/2024 | Approved | REGINA MENDEZ |
| Drywall Nailing | 8/12/2024 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Final | 8/12/2024 | Corrections Issued | REGINA MENDEZ |
| Smoke Detectors | 8/12/2024 | Corrections Issued | REGINA MENDEZ |
| Sewer | 12/2/2024 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 2/20/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/5/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/7/2025 | Corrections Issued | BOBBY KEY |
| Gas Test | 3/7/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 3/7/2025 | Approved | BOBBY KEY |
| PLUMBING-Final | 3/7/2025 | Corrections Issued | BOBBY KEY |
| Smoke Detectors | 3/7/2025 | Approved | BOBBY KEY |
| Special/Order Compliance | 3/7/2025 | Partial Inspection | WILBER ROSALES |
| ELECTRICAL-Final | 3/12/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Gas Test | 3/12/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 3/12/2025 | Partial Approval | ASHLEY THOMPSON |
| Gas Test | 3/13/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 3/13/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 4/7/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 4/9/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 4/9/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 4/9/2025 | Approved | ASHLEY THOMPSON |
| Deputy Drilled-In Anchors | 4/11/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 4/11/2025 | Conditional Approval | MICHAEL PELHAM |
| Special/Order Compliance | 4/14/2025 | Corrections Issued | MICHAEL PELHAM |
| Final | 4/16/2025 | Partial Approval | KIRK SANDERS |
| Final | 4/24/2025 | OK to Issue CofO | MICHAEL PELHAM |
| Service/Power Release | 4/24/2025 | Approved | MICHAEL PELHAM |