3614 S MEIER ST 90066
Certificate Information: 3614 S MEIER ST 90066
- Application / Permit
- 22014-30000-04013
- Plan Check / Job No.
- B22WL03032
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story S.F.R. addition w/ a (n) attached garage and roof trusses
- Permit Issued
- Issued on 11/8/2022
- Issuing Office
- Current Status
- CofO Issued on 10/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | KAVIAN REFAHI |
| Corrections Issued | 8/14/2022 | KAVIAN REFAHI |
| Quality Review Completed | 8/30/2022 | TARIK SAOUD |
| Plan Check Approved | 11/7/2022 | KAVIAN REFAHI |
| Issued | 11/8/2022 | APPLICANT |
| Building Plans Picked Up | 1/10/2023 | APPLICANT |
| CofO in Progress | 9/27/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 10/7/2023 | DANIEL ORRANTE |
| CofO Issued | 10/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 9/19/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2022 | DINAH GARIN |
| Sewer availability | Cleared | 9/20/2022 | DINAH GARIN |
| Trees in Parkway | Cleared | 9/21/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 10/11/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/14/2022 | DINAH GARIN |
| GPI Written Notices | Cleared | 11/7/2022 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 11/7/2022 | KAVIAN REFAHI |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/17/2023 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 4/5/2023 | Approved | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 4/6/2023 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 5/18/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Sewer | 5/18/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/19/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/24/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/24/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/24/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/25/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 5/25/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 5/30/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/30/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/1/2023 | No Access for Inspection | EVAN COOPER |
| Green Building Rough | 6/1/2023 | No Access for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/6/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/8/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 6/22/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/22/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/22/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| HVAC-Final | 8/30/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Gas Test | 9/5/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 9/5/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/5/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 9/6/2023 | Approved | MICHAEL PELHAM |
| Final | 9/26/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 9/26/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 9/26/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 9/26/2023 | Approved | JESUS RODRIGUEZ |