3614 S MEIER ST 90066

Certificate Information: 3614 S MEIER ST 90066

Application / Permit
22014-30000-04013
Plan Check / Job No.
B22WL03032
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story S.F.R. addition w/ a (n) attached garage and roof trusses
Permit Issued
Issued on 11/8/2022
Issuing Office
Current Status
CofO Issued on 10/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 KAVIAN REFAHI
Corrections Issued 8/14/2022 KAVIAN REFAHI
Quality Review Completed 8/30/2022 TARIK SAOUD
Plan Check Approved 11/7/2022 KAVIAN REFAHI
Issued 11/8/2022 APPLICANT
Building Plans Picked Up 1/10/2023 APPLICANT
CofO in Progress 9/27/2023 JESUS RODRIGUEZ
Permit Finaled 10/7/2023 DANIEL ORRANTE
CofO Issued 10/7/2023 DANIEL ORRANTE
Permit Finaled 10/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 9/19/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/20/2022 DINAH GARIN
Sewer availability Cleared 9/20/2022 DINAH GARIN
Trees in Parkway Cleared 9/21/2022 ADALBERTO VERA
Low Impact Development Cleared 10/11/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 10/14/2022 DINAH GARIN
GPI Written Notices Cleared 11/7/2022 KAVIAN REFAHI
Grading Pre-Inspection Cleared 11/7/2022 KAVIAN REFAHI

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/17/2023 Partial Approval EVAN COOPER
Footing/Foundation/Slab 4/5/2023 Approved JESUS RODRIGUEZ
Deputy Reinf. Concrete 4/6/2023 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 4/19/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Partial Approval EVAN COOPER
Deputy Wood Construction 5/18/2023 Conditional Approval JESUS RODRIGUEZ
Sewer 5/18/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/19/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 5/24/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 5/24/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/24/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 5/25/2023 Approved JESUS RODRIGUEZ
Shower Pan 5/25/2023 Approved JESUS RODRIGUEZ
Green Building Rough 5/30/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/30/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/1/2023 No Access for Inspection EVAN COOPER
Green Building Rough 6/1/2023 No Access for Inspection EVAN COOPER
BUILDING-Rough-Frame 6/6/2023 Approved JESUS RODRIGUEZ
Green Building Rough 6/6/2023 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 6/6/2023 Approved JESUS RODRIGUEZ
Insulation 6/8/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 6/22/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/22/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 8/22/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Approved JESUS RODRIGUEZ
HVAC-Final 8/30/2023 Corrections Issued JESUS RODRIGUEZ
Gas Test 9/5/2023 Approved JESUS RODRIGUEZ
HVAC-Final 9/5/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Final 9/5/2023 Approved JESUS RODRIGUEZ
Service/Power Release 9/6/2023 Approved MICHAEL PELHAM
Final 9/26/2023 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 9/26/2023 Approved JESUS RODRIGUEZ
HVAC-Final 9/26/2023 Approved JESUS RODRIGUEZ
Smoke Detectors 9/26/2023 Approved JESUS RODRIGUEZ