11731 W HATTERAS ST 91607
Certificate Information: 11731 W HATTERAS ST 91607
- Application / Permit
- 22014-30000-03968
- Plan Check / Job No.
- B22WL03022
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Add to and convert (E) detached garage to ADU per LAMC 12.22A33(c) & (d) in the rear of the lot.
- Permit Issued
- Issued on 9/14/2022
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | JAHANSHAH POURHASSAN |
| Corrections Issued | 8/19/2022 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 9/13/2022 | JAHANSHAH POURHASSAN |
| Issued | 9/14/2022 | APPLICANT |
| Building Plans Picked Up | 9/26/2022 | APPLICANT |
| CofO in Progress | 11/28/2023 | RYAN SALAZAR |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
| CofO Issued | 3/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 8/23/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/24/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 8/31/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | J G Builders Inc; Lic. No.: 1049536-B | 4418 LA MADERA AVENUE EL MONTE, CA 91732 |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/8/2022 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 11/16/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/16/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/21/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/21/2022 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 2/22/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/7/2023 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 3/7/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 3/7/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/7/2023 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 3/7/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/3/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 4/3/2023 | Approved | JOHN HAYES |
| Green Building Rough | 4/3/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 4/3/2023 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 4/3/2023 | Approved | JOHN HAYES |
| Wood Frame | 4/3/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 4/7/2023 | Approved | ROBERT GOLD |
| HVAC-Rough | 4/7/2023 | Approved | ROBERT GOLD |
| PLUMBING-Rough | 4/7/2023 | Approved | ROBERT GOLD |
| Special/Order Compliance | 4/7/2023 | Approved | JOHN HAYES |
| Wood Frame | 4/7/2023 | Partial Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/11/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Rough | 4/11/2023 | Approved | ROBERT GOLD |
| Pre-Inspection | 4/21/2023 | Approved | JOHN COLEMAN |
| Insulation | 5/2/2023 | Corrections Issued | ROBERT GOLD |
| Interior/Exterior Lathing | 5/2/2023 | Corrections Issued | ROBERT GOLD |
| Insulation | 5/11/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 5/11/2023 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 5/31/2023 | Approved | JOHN HAYES |
| Shower Pan | 9/8/2023 | Approved | JENNIFER RABUCHIN |
| Sewer | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/21/2023 | Approved | RYAN SALAZAR |
| Final | 11/21/2023 | Partial Inspection | RYAN SALAZAR |
| Green Building Final | 11/21/2023 | Partial Approval | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 11/21/2023 | Approved | RYAN SALAZAR |
| Final | 11/27/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 11/27/2023 | Approved | RYAN SALAZAR |
| Service/Power Release | 11/27/2023 | Approved | RYAN SALAZAR |