12514 W RYE ST 91604

Certificate Information: 12514 W RYE ST 91604

Application / Permit
22014-30000-03947
Plan Check / Job No.
B22WL03010
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and Remodel to an (E) 1-Story S.F.D w/Attached Garage
Permit Issued
Issued on 10/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2022 APPLICANT
Assigned to Plan Check Engineer 8/17/2022 DAVID CASTILLO
Corrections Issued 8/18/2022 DAVID CASTILLO
Plan Check Approved 9/7/2022 EDWIN ESPIN
Building Plans Picked Up 9/12/2022 APPLICANT
Issued 10/20/2022 APPLICANT
CofO in Progress 10/6/2023 CHRISTOPHE COCHRAN
Permit Finaled 10/1/2024 DANIEL ORRANTE
CofO Issued 10/1/2024 DANIEL ORRANTE
Permit Finaled 10/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/26/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 8/26/2022 ROMAN GUTIERREZ
Sewer availability Cleared 8/26/2022 ROMAN GUTIERREZ

Contact Information

Architect Keck,, Krystyan Elizabeth; Lic. No.: C29385 12322 GREENE AVENUE      LOS ANGELES, CA 90066
Contractor Cardenas Oskar; Lic. No.: 1020558-B 431 ORANGE GROVE AVE      SAN FERNANDO, CA 91340
Engineer Lotfi,, Fariborz Frank; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/7/2022 Approved JACK KARGODORIAN
Wood Frame 12/15/2022 Partial Approval WILLIAM WREN
BUILDING-Rough-Frame 2/10/2023 Partial Approval ROBERT GOLD
Deputy Wood Construction 2/10/2023 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 2/10/2023 Corrections Issued ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Approved ROBERT GOLD
Green Building Rough 2/10/2023 Not Ready for Inspection ROBERT GOLD
HVAC-Rough 2/10/2023 Corrections Issued ROBERT GOLD
PLUMBING-Rough 2/10/2023 Approved ROBERT GOLD
BUILDING-Rough-Frame 2/23/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/23/2023 Approved CHRISTOPHE COCHRAN
Green Building Rough 2/23/2023 Approved CHRISTOPHE COCHRAN
HVAC-Rough 2/23/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/23/2023 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Rough 3/6/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 3/6/2023 Approved JOHN COLEMAN
Insulation 3/10/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 3/17/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/28/2023 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 3/28/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 8/30/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 9/11/2023 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Final 10/4/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 10/4/2023 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 10/4/2023 Approved CHRISTOPHE COCHRAN
HVAC-Final 10/4/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 10/4/2023 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 10/4/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 10/6/2023 Approved CHRISTOPHE COCHRAN
Final 10/6/2023 OK to Issue CofO CHRISTOPHE COCHRAN
HVAC-Final 10/6/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 10/6/2023 Approved CHRISTOPHE COCHRAN