7837 S EL MANOR AVE 90045
Certificate Information: 7837 S EL MANOR AVE 90045
- Application / Permit
- 22014-30000-03819
- Plan Check / Job No.
- B22WL02913
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel, new windows & doors, new addition of screened in porch to the rear of the (E) SFD.
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | JASON JANGADA |
| Corrections Issued | 8/4/2022 | JASON JANGADA |
| Applicant returned to address corrections | 8/19/2022 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 9/1/2022 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 9/1/2022 | APPLICANT |
| Issued | 9/7/2022 | APPLICANT |
| CofO in Progress | 9/25/2023 | RICHARD STEINBACH |
| Permit Finaled | 9/27/2023 | DANIEL ORRANTE |
| CofO Issued | 9/27/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/27/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/10/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 8/23/2022 | JASON JANGADA |
Contact Information
| Architect | Le, Clerc, Sarah Jane; Lic. No.: C39716 | 1134 CHELSEA AVE #B SANTA MONICA, CA 90403 |
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
| Engineer | Hansen,, Neil Christian; Lic. No.: L9027 | 1545 VICTORY BLVD 2ND FLOOR N.C. HANSEN INC. GLENDALE, CA 91201 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/27/2022 | Corrections Issued | HERBERT GIRON |
| METHANE-Barrier | 9/27/2022 | Approved | HERBERT GIRON |
| METHANE-Subgrade | 9/27/2022 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 9/29/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Corrections Issued | HERBERT GIRON |
| Wood Frame | 1/25/2023 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Wood Construction | 1/27/2023 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 2/10/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 2/16/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 2/16/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 3/1/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 3/6/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 3/6/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/9/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Approved | HERBERT GIRON |
| Green Building Final | 3/9/2023 | Corrections Issued | HERBERT GIRON |
| METHANE-Rough | 3/9/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/14/2023 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 3/14/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 3/14/2023 | Approved | HERBERT GIRON |
| Insulation | 3/22/2023 | Approved | HERBERT GIRON |
| Special/Order Compliance | 3/22/2023 | Partial Inspection | JESUS PINEDA |
| Drywall Nailing | 3/30/2023 | Corrections Issued | HERBERT GIRON |
| Drywall Nailing | 3/31/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 3/31/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/31/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 7/31/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 8/29/2023 | Corrections Issued | HERBERT GIRON |
| Final | 8/29/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 8/29/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 8/29/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 8/29/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Not Required | HERBERT GIRON |
| Smoke Detectors | 8/29/2023 | Approved | HERBERT GIRON |
| Special/Order Compliance | 8/29/2023 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 9/14/2023 | Approved | HERBERT GIRON |
| Final | 9/14/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 9/14/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 9/14/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 9/14/2023 | Approved | HERBERT GIRON |
| Final | 9/22/2023 | Conditional Approval | HERBERT GIRON |
| Green Building Final | 9/22/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 9/22/2023 | Approved | HERBERT GIRON |