7837 S EL MANOR AVE 90045

Certificate Information: 7837 S EL MANOR AVE 90045

Application / Permit
22014-30000-03819
Plan Check / Job No.
B22WL02913
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel, new windows & doors, new addition of screened in porch to the rear of the (E) SFD.
Permit Issued
Issued on 9/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 JASON JANGADA
Corrections Issued 8/4/2022 JASON JANGADA
Applicant returned to address corrections 8/19/2022 JAHANSHAH POURHASSAN
Plan Check Approved 9/1/2022 JAHANSHAH POURHASSAN
Building Plans Picked Up 9/1/2022 APPLICANT
Issued 9/7/2022 APPLICANT
CofO in Progress 9/25/2023 RICHARD STEINBACH
Permit Finaled 9/27/2023 DANIEL ORRANTE
CofO Issued 9/27/2023 DANIEL ORRANTE
Permit Finaled 9/27/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/10/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 8/11/2022 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 8/23/2022 JASON JANGADA

Contact Information

Architect Le, Clerc, Sarah Jane; Lic. No.: C39716 1134 CHELSEA AVE #B      SANTA MONICA, CA 90403
Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,
Engineer Hansen,, Neil Christian; Lic. No.: L9027 1545 VICTORY BLVD 2ND FLOOR   N.C. HANSEN INC.    GLENDALE, CA 91201

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/27/2022 Corrections Issued HERBERT GIRON
METHANE-Barrier 9/27/2022 Approved HERBERT GIRON
METHANE-Subgrade 9/27/2022 Approved HERBERT GIRON
Footing/Foundation/Slab 9/29/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Corrections Issued HERBERT GIRON
Wood Frame 1/25/2023 Not Ready for Inspection HERBERT GIRON
Deputy Wood Construction 1/27/2023 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 2/10/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 2/16/2023 Approved JESUS RODRIGUEZ
Shower Pan 2/16/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 3/1/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 3/6/2023 Approved HERBERT GIRON
HVAC-Rough 3/6/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/9/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Approved HERBERT GIRON
Green Building Final 3/9/2023 Corrections Issued HERBERT GIRON
METHANE-Rough 3/9/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/14/2023 Partial Approval HERBERT GIRON
Green Building Rough 3/14/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 3/14/2023 Approved HERBERT GIRON
Insulation 3/22/2023 Approved HERBERT GIRON
Special/Order Compliance 3/22/2023 Partial Inspection JESUS PINEDA
Drywall Nailing 3/30/2023 Corrections Issued HERBERT GIRON
Drywall Nailing 3/31/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 3/31/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 7/31/2023 Approved HERBERT GIRON
HVAC-Final 7/31/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 8/29/2023 Corrections Issued HERBERT GIRON
Final 8/29/2023 Corrections Issued HERBERT GIRON
Green Building Final 8/29/2023 Corrections Issued HERBERT GIRON
HVAC-Final 8/29/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/29/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Not Required HERBERT GIRON
Smoke Detectors 8/29/2023 Approved HERBERT GIRON
Special/Order Compliance 8/29/2023 Partial Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 9/14/2023 Approved HERBERT GIRON
Final 9/14/2023 Corrections Issued HERBERT GIRON
Green Building Final 9/14/2023 Corrections Issued HERBERT GIRON
HVAC-Final 9/14/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 9/14/2023 Approved HERBERT GIRON
Final 9/22/2023 Conditional Approval HERBERT GIRON
Green Building Final 9/22/2023 Approved HERBERT GIRON
HVAC-Final 9/22/2023 Approved HERBERT GIRON