13006 W CALVERT ST 91401
Certificate Information: 13006 W CALVERT ST 91401
- Application / Permit
- 22014-30000-03594
- Plan Check / Job No.
- B22WL02797
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel to (E) SFD, square footage addition and new trellis at rear of the SFD
- Permit Issued
- Issued on 11/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2022 | EDWIN ESPIN |
| Corrections Issued | 8/2/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 12/7/2022 | EDWIN ESPIN |
| Plan Check Approved | 12/22/2022 | AMY GUEVARRA |
| Issued | 11/17/2023 | APPLICANT |
| CofO in Progress | 9/3/2024 | OGANES TARAKHCHYAN |
| CofO Issued | 9/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2022 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/21/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/21/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/23/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 1/24/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 3/7/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 3/15/2024 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 4/18/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 4/18/2024 | Approved | KIRK SANDERS |
| Green Building Rough | 4/18/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 4/18/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 4/18/2024 | Corrections Issued | KIRK SANDERS |
| Deputy Wood Construction | 4/19/2024 | Conditional Approval | JUAN VALENZUELA |
| Gas Test | 4/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/23/2024 | Approved | JOSE AVILA |
| Green Building Rough | 4/23/2024 | Approved | JOSE AVILA |
| Insulation | 4/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 5/1/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/1/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 5/6/2024 | Approved | SALVADOR MARTINEZ |
| Final | 7/9/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 8/27/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 8/27/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/27/2024 | Approved | OGANES TARAKHCHYAN |