6716 N CANTALOUPE AVE 91405

Certificate Information: 6716 N CANTALOUPE AVE 91405

Application / Permit
22014-30000-03499
Plan Check / Job No.
B22WL02745
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition only of new patio and study room to (E) SFD per engineered design
Permit Issued
Issued on 8/22/2022
Issuing Office
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/27/2022 RICHARD GARCIA
Corrections Issued 7/28/2022 RICHARD GARCIA
Applicant returned to address corrections 8/9/2022 JASON JANGADA
Plan Check Approved 8/22/2022 JASON JANGADA
Issued 8/22/2022 APPLICANT
Building Plans Picked Up 8/24/2022 APPLICANT
CofO in Progress 2/24/2023 RYAN SALAZAR
Permit Finaled 4/18/2023 MICHAEL SMITH
CofO Issued 4/18/2023 MICHAEL SMITH
Permit Finaled 4/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/4/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 8/4/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 8/4/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 8/4/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 8/4/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/30/2022 Approved RYAN SALAZAR
Wood Frame 12/13/2022 Partial Approval JOHN COLEMAN
BUILDING-Rough-Frame 12/20/2022 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 12/20/2022 Approved RYAN SALAZAR
Final 12/20/2022 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 12/20/2022 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 12/20/2022 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Not Ready RYAN SALAZAR
Wood Frame 12/22/2022 Approved JOHN COLEMAN
Drywall Nailing 12/28/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/28/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/8/2023 Approved RYAN SALAZAR
Final 2/8/2023 Corrections Issued RYAN SALAZAR
Green Building Final 2/8/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 2/8/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 2/8/2023 Approved RYAN SALAZAR
Final 2/24/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 2/24/2023 Approved RYAN SALAZAR