12001 W CREST CT 90210
Certificate Information: 12001 W CREST CT 90210
- Application / Permit
- 22014-30000-03471
- Plan Check / Job No.
- B22WL02715
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition (27 sf) to the first floor of (e) 2-story SFD w./ att. garage and remodel
- Permit Issued
- Issued on 2/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | REZA HAGHIGHAT |
| Corrections Issued | 8/10/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 8/22/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 1/5/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 2/1/2023 | REZA HAGHIGHAT |
| Issued | 2/7/2023 | APPLICANT |
| CofO in Progress | 3/14/2025 | MISAEL ESPARZA |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
| CofO Issued | 4/8/2025 | RUBEN SALAS |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/26/2022 | OLGA AYALA |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 11/30/2022 | COLIN LOREDO |
| Private street | Cleared | 12/2/2022 | NELSON RODRIGUEZ |
| Hydrant and Access approval | Cleared | 12/13/2022 | RUEL COLE |
| Low Impact Development | Cleared | 1/17/2023 | CHRIS VONG |
| Grading Pre-Inspection | Cleared | 1/19/2023 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 2/1/2023 | JENSON LEE |
Contact Information
| Contractor | Mir Construction Inc; Lic. No.: 930423-B | 16656 CHAPLIN AVENUE ENCINO, CA 91436 |
| Engineer | Shirley,, Peter; Lic. No.: C75050 | 4429 DAWES AVE CULVER CITY, CA 90230 |
| Geologist | , ; Lic. No.: GEO2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/28/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/12/2023 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/2/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/15/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/28/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/5/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/15/2023 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 9/15/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | JOHN COLEMAN |
| Green Building Rough | 10/12/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 10/12/2023 | Approved | JOHN COLEMAN |
| Insulation | 11/16/2023 | Approved | JOHN COLEMAN |
| Drywall Nailing | 12/6/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 1/16/2024 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 1/23/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 1/27/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 2/6/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 2/10/2025 | Partial Approval | JACK KARGODORIAN |
| HVAC-Final | 2/13/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Final | 2/20/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/27/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 2/27/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 2/27/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 2/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 3/12/2025 | OK to Issue CofO | MISAEL ESPARZA |